Learning guide · Building Management & HVAC

Qatar HVAC Design Review Guide

A three-week learning path for engineers who must review HVAC deliverables on Qatar industrial and township projects: psychrometrics for a latent-load coast, cooling loads and HAP reports, ASHRAE 62.1 ventilation and pressurisation, VRF and packaged systems at 47 °C, ducts and piping, special rooms, Civil Defence interfaces, Kahramaa and GSAS compliance, and commissioning. Where the text says “the design basis”, substitute your own project’s Basis of Design; the numeric criteria quoted are typical Gulf values for illustration.

Path 13 modules · 3 weeks · about 24 hours Order load calculations → equipment → ducts and piping → special rooms → fire, controls, commissioning Built 3 September 2026 Scope generic edition; no project-specific data

Week 1 · Module 0 · about 1 hour

Orientation: what you are reviewing, against what, and in what order

Before any HVAC theory, fix three things: the documents that will land on your desk, the hierarchy of rules they must satisfy, and the vocabulary that lets you locate a problem in seconds. This module also places you with a ten-question diagnostic so you can skip what you already know.

Why it matters

A reviewer's failure mode is not ignorance of HVAC. It is checking a deliverable against the wrong yardstick: accepting a load calculation because the arithmetic is right while the design condition it started from is not the contractual one, or rejecting a duct size against ASHRAE guidance when the project specification says something stricter. Every module in this guide therefore has the same spine: concept → what the design basis says → what the reference says → what the Qatar rule says → what you check.

Think of the Basis of Design (design basis) the way you think of a pump datasheet's rated point. It is the point everything downstream is guaranteed against. If the detailed design silently moves that point, every selection built on it inherits the shift.

The document you review against

Every project has a Basis of Design (design basis) or Design Basis Memorandum: the document that freezes site conditions, indoor criteria, system philosophy and the code hierarchy before detailed design starts. Read it end to end once, then keep its design-criteria tables open beside every deliverable you review. If your project has no design basis, the first review comment you write is a request for one.

The hierarchy of rules

Qatar has no unified national building code. What governs an HVAC design is a stack, and the order of the stack is contractual, not a matter of engineering taste. When two documents disagree, the one higher in the stack wins; when the higher one is silent, you drop one level.

LevelInstrumentWhat it fixes for HVACWhere you find it
1Client corporate engineering standards and philosophies (in oil and gas: the operator's building-services minimum requirements, fire and safety philosophy, commissioning procedure)Design conditions, criticality, pressurisation of buildings, fire and gas interfaces, gas-tight dampers, documentation and handoverContract appendices. verify clause Not public; obtain the project copies before quoting clause numbers.
2Qatar Construction Specifications, QCS 2014 (QS 27:2014), mandatory since May 2015; QCS 2024 (QS 27/2024) published as an optional standard that "supersedes" 2014Section 22 Air Conditioning, Refrigeration and Ventilation (Parts 1–9); Section 9 Part 22 ventilation of infrastructure plant; Sections 14/15 insulation; Section 21 electrical; Section 23 fireqcs.qs.gov.qa. Fix the edition in the contract;
2Kahramaa: Energy & Water Conservation Code (2016; re-issued 2025 as CN-CNT-P2-C2 Issue 2), Electricity Wiring Code 2018, QS 2663 air-conditioner star ratingEnvelope U-values (wall 0.568 W/m²K), cooling-load submittal, minimum EER/COP by equipment class, electrical supply data and AC load declarationkm.qa service regulations;
2Qatar Civil Defence (QCDD): Civil Defence Technical Requirements Guide 2022 (2023 update) on top of the 2015 Fire Safety Guidelines annexes (ACMV_N1 for air-conditioning and mechanical ventilation)Smoke control, pressurisation, fire dampers, HVAC shutdown on alarm, kitchen exhaust, generator and pump-room ventilation, fire command centre; NFPA adopted where the guide is silentMoI guide PDF; approvals at DC1 (life safety) and DC2 (fire alarm, firefighting, mechanical ventilation)
2GSAS (GORD) Design & Build 2019Energy E.1/E.2, Indoor Environment IE.1 thermal comfort, IE.2 natural ventilation, IE.3 mechanical ventilationgsas.gord.qa.
3International codes as referenced: ASHRAE 62.1-2022, 55, 170, 52.2, 90.1, Handbooks; NFPA 90A, 92, 96, 37, 101, 5000; SMACNA / DW/144; AMCA, AHRI, ISO 12944, BS EN 12101-6, EN 50272-2Ventilation rates, comfort, filtration, duct construction, smoke control, equipment ratings, corrosion classesThe design basis's code list; the precedence clause usually reads "local regulations take precedence over international codes".

Trap. A designer who cites "ASHRAE" for a value that a Level-1 or Level-2 document also fixes is not wrong, only incomplete. Your comment should name the higher document and ask for the comparison, not merely reject the ASHRAE value.

What will arrive, and the order this guide follows

DeliverableTypical contentModuleFirst thing to open
Heat-load calculations (Carrier HAP)Weather file, space inputs, envelope library, schedules, zone and system loads, psychrometricsM1, M2, M3The design-conditions page and the safety factors, before any result
Equipment schedules and datasheetsVRF outdoor/indoor units, packaged units, splits, TFAHU/FAHU/ERU, fans, ecology unitsM4, M5The rating condition of the stated capacity
Duct and pipe sizing, layouts, schematicsDuct sizing tables, refrigerant pipe routing, condensate, insulation, dampersM6, M7The friction rate and velocity limits used
Special-room ventilation and pressurisationSubstations, battery rooms, pump/generator rooms, kitchens, laundry, fire command centreM8, M9Whether the stated ACH is supply, recirculation or outdoor air
Controls, BMS, energy complianceDDC architecture, points list, BACnet, Kahramaa and GSAS submittalsM10The interlock and alarm matrix
Testing, balancing, commissioning, handoverDuct leakage, TAB reports, pre-commissioning and commissioning recordsM11The tolerance basis stated on the report

How to work this guide

  • Budget: three weeks, 20–30 hours. Module hours are shown in the rail. Do the modules in order the first time; afterwards use the rail as a lookup.
  • Active recall: each module ends with a self-check and flashcards. Answer before revealing. If you get fewer than four of six, re-read the concept block, not the answer.
  • Checklists persist on this device (browser storage). Tick items as you apply them to a real deliverable; the rail shows completion.
  • Calculators (Modules 1, 3, 6, 8) run in the page with no external calls. Use them to reproduce a designer's number, not to replace their calculation.
  • Badges: Verified public source opened or confirmed by an authoritative snippet; Partial existence confirmed, clause content second-hand; Unverified cite only after you obtain the document; design basis quoted from the project Basis of Design.

Diagnostic: place yourself

Answer all ten in your head first. Fewer than 5 right: do every module. 5–7: skim M1, do the rest. 8+: go straight to the module matching the first document you will receive, then return to M12.

  1. Air at 47 °C dry-bulb and 30 °C wet-bulb: roughly what is its relative humidity, and why does that matter less than its dew point?

  2. Which single number in a cooling-load report tells you the most about whether the coil will hold 50 % RH?

  3. ASHRAE 62.1: write the breathing-zone ventilation equation.

  4. What is the difference between "10 ACH" as a ventilation requirement and "10 ACH" as a supply-air rate?

  5. A VRF outdoor unit datasheet says 28 kW cooling. What condition is that at, and what do you need instead?

  6. Name the duct construction standard most Qatar specifications cite and its leakage classes.

  7. Why must refrigerant suction risers respect a minimum velocity, and what happens if the compressor unloads?

  8. What is a sand-trap louvre sized for, and at what face velocity?

  9. Which authority in Qatar approves smoke-control and mechanical-ventilation drawings, and at which stage?

  10. Kahramaa's minimum efficiency for a split air conditioner is stated at two test conditions. What are they and which is the harder one?

Next: Module 1, psychrometrics and the Qatar climate.

Week 1 · Module 1 · about 2.5 hours

Psychrometrics and the Qatar climate

Every HVAC number on this project descends from a handful of air states. Learn to read them off the chart, compute them, and notice when a designer has mixed two of them up. The Gulf coast is a latent-load climate; a reviewer who thinks only in dry-bulb temperature will approve undersized coils.

Why it matters

Gulf design bases typically fix two outdoor points: a peak dry-bulb condition for envelope and sensible loads, and a high-wet-bulb or high-dew-point condition for outside-air (latent) loads. If you cannot say within a minute why a 34 °C DB / 32 °C WB point carries more energy than a 47 °C DB / 30 °C WB one, you cannot review the fresh-air unit selections.

Concept

Five properties, two of which travel with the air

  • Dry-bulb temperature (DB, °C): what a thermometer reads. Drives sensible load.
  • Humidity ratio (w, g of water per kg of dry air): the moisture content. It does not change when air is simply heated or cooled above its dew point, so it is the quantity that identifies an air stream through a system.
  • Relative humidity (RH, %): moisture content relative to saturation at that temperature. Useful for comfort and corrosion statements; useless for tracking air through a coil, because it changes every time the temperature does.
  • Wet-bulb temperature (WB, °C): the temperature reached by evaporative cooling; a stand-in for enthalpy. Coils and cooling towers are rated by it.
  • Enthalpy (h, kJ/kg dry air): total heat content, sensible plus latent. Differences in enthalpy give total coil loads directly.
  • Dew point (DP, °C): the temperature at which the air starts to condense. Every surface colder than the dew point sweats. This is the number that decides insulation thickness in Qatar.

The three SI air-side equations

With Q in m³/s, the standard-air constants at sea level are:

q_sensible (kW) = 1.2 × Q × ΔT q_latent (kW) = 3.0 × Q × Δw (g/kg) q_total (kW) = 1.2 × Q × Δh

The ASHRAE Handbook writes the same set with Q in L/s as 1.23 × Q × ΔT (W), 3010 × Q × Δw (W, w in kg/kg) and 1.20 × Q × Δh (W). The psychrometric chart in your library prints them as 1.2, 2.98 and 1.19. All three sets agree within 2 %; the differences come from the density assumed. What you must not do is mix a metric constant with imperial units (the imperial set is 1.08, 4840 and 4.5 with CFM).

Why peak dry-bulb is not peak load

Outdoor air is expensive to condition in proportion to its enthalpy, not its temperature. A very hot afternoon in the desert is dry; a humid morning with sea breeze is cooler but wetter. Compare the two design basis points:

StateDB °CWB °CRH %w g/kgh kJ/kgDew point °CUse
design basis Ambient design473029.619.998.824.9Envelope, sensible peak, equipment ambient
design basis Outside-air load basis343286.929.8110.531.5Fresh-air coils, dehumidification
Dubai Green Building Regulations 501.03462928.818.493.723.5Regional comparison
Room 22 °C / 50 %2215.6508.243.011.1Accommodation and most amenities
Room 23 °C / 50 %2316.4508.845.412.0Mess hall, workshop, laundry, substations
Room 24 °C / 50 %2417.1509.347.812.9Pump rooms; common Gulf default
TFAHU off-coil 20 °C / 50 %2013.9507.338.69.3Treated fresh air delivered to spaces
Computed with ASHRAE Fundamentals Chapter 1 relations at 101.325 kPa (the site is at sea level). Reproduce any row with the calculator below.

The 34/32 point has 12 % more enthalpy and 50 % more moisture than the 47/30 point. For a treated-fresh-air unit the coil load at 34/32 is about 19 % higher than at 47/30, and the sensible-heat ratio of that load is around 0.2: it is a dehumidifier first and a cooler second. That is why Gulf fresh-air units carry heat pipes or hot-gas reheat: the air must be cooled below its target dew point to wring the moisture out, then reheated so the space does not overcool.

Where the design conditions come from, and what "0.4 %" means

ASHRAE Handbook Fundamentals Chapter 14 tabulates, for Doha International Airport (WMO 411700), the dry-bulb temperature exceeded 0.4 %, 1 % and 2 % of the hours in a year, each with its mean coincident wet-bulb, and separately the wet-bulb, dew-point and enthalpy exceeded for the same fractions with their coincident dry-bulbs. Two consequences:

  • The 0.4 % dry-bulb for Doha is in the mid-40s with a coincident wet-bulb in the low-to-mid 20s. A design value of 47 °C DB with 30 °C WB is therefore already a margin above the statistical peak and combines a hot dry-bulb with a wet-bulb that does not statistically occur with it. That is a client choice, not an error; you should know it is conservative.
  • The 0.4 % wet-bulb and dew-point for Doha are around 31 °C and 30 °C respectively, with coincident dry-bulbs in the mid-30s. The 34/32 basis sits at the extreme of that band. Fresh-air coils selected on it will be conservative; fresh-air coils selected on 47/30 alone will be undersized on latent duty.

QCS 2014 fixes a third set of numbers that are not load conditions at all but equipment ratings: continuous operation at a maximum daily-average ambient of 50 °C, an operating range of 0–55 °C, and a design humidity of 100 %. These rate the hardware. Never feed "50 °C and 100 % RH" into a coil selection; that state does not exist in Doha's record and would produce absurd loads.

Common confusion. "Design ambient 47 °C" is used loosely for three different things: the cooling-load outdoor DB, the condensing-unit rating ambient, and the equipment survival ambient. A VRF condenser must still deliver capacity at 47 °C (or the design basis's 55 °C without tripping), which is a rating-curve question (Module 5), not a psychrometric one.

Read

  • A
    Psychrometric chart (CIBSE-style, sea level) — the legend constants 1.2 / 2.98 / 1.19 and the chart itself. Plot the seven states in the table above by hand once; it is the fastest way to make the shape of the problem stick.
  • B
    1997 ASHRAE Fundamentals Ch. 28 (SI) — pages 28.9–28.10: the 1.23 / 3010 / 1.20 constants and their derivation, including the altitude correction you will not need at sea level.
  • C
    PDH M196 "HVAC Made Easy" — Part 7, ventilation and infiltration, and the worked comparison showing that using the WB design condition raises the ventilation load by 23–49 % over the DB/MCWB condition. Imperial units; read for the argument, not the numbers.
  • D
    Basics of Manual Cooling Load Calculation (Castillo, Part 1) — the Dubai worked room at 47 °C / 29.5 °C WB, h = 96 kJ/kg outside against 48 kJ/kg supply. SI throughout; the closest analogue in the library to this project.

Qatar rules that touch this module

  • Partial
    QCS 2014 Section 22 Part 1 (design data) — equipment suitable for 0–55 °C, continuous operation at 50 °C maximum daily-average ambient, 20–100 % humidity with 100 % design humidity; solar loads on maximum instantaneous values with the worst cumulative hourly block 10:00–18:00, May–October. Clause numbers to be confirmed from the Section 22 PDF.
  • Verified
    ASHRAE Fundamentals 2021 Ch. 14 / Standard 169-2021 — Doha station 411700; Standard 169-2021 introduces Climate Zone 0 (extremely hot); confirm the dataset year the HAP weather file uses (ashrae-meteo.info).
  • Verified
    Dubai Municipality Green Building Regulations 501.03 — 46 °C DB / 29 °C WB, 24 °C / 50 ± 5 % indoors, daily range 13.8 K, safety factors capped at 10 % sensible / 5 % latent. Not law in Qatar; the best published regional benchmark for challenging a Qatar basis.

State-point calculator

Enter dry-bulb and either RH or wet-bulb. Sea-level pressure 101.325 kPa; ASHRAE Fundamentals Chapter 1 relations.

Humidity ratio g/kg
Enthalpy kJ/kg
RH %
Wet-bulb °C
Dew point °C
Specific volume m³/kg

Outdoor-air load calculator

Load to bring outdoor (or infiltration) air to an indoor or off-coil state. Constants: 1.2 kJ/(m³·K) sensible, 3010 W per (L/s)(kg/kg) latent, 1.2 kg/m³ × Δh total.

Sensible kW
Latent kW
Total kW
Total TR
Sensible-heat ratio
Enthalpy path kJ/kg

Worked example: 100 L/s of outdoor air, two design points

1
Target state: room air 22 °C / 50 % → w = 8.2 g/kg, h = 43.0 kJ/kg.
2
At 47 °C / 30 °C WB (w = 19.9 g/kg, h = 98.8 kJ/kg): sensible 1.2 × 0.1 × 25 = 3.0 kW; latent 3010 × 100 × (0.0199 − 0.0082) / 1000 = 3.5 kW; total by enthalpy 1.2 × 0.1 × (98.8 − 43.0) = 6.7 kW. SHR ≈ 0.45.
3
At 34 °C / 32 °C WB (w = 29.8 g/kg, h = 110.5 kJ/kg): sensible 1.2 × 0.1 × 12 = 1.4 kW; latent 3010 × 100 × (0.0298 − 0.0082) / 1000 = 6.5 kW; total 1.2 × 0.1 × (110.5 − 43.0) = 8.1 kW. SHR ≈ 0.18.
The cooler, wetter point costs 21 % more total cooling and four times the latent duty. A fresh-air coil selected at 47/30 would be short on dehumidification exactly on the mornings the accommodation rooms are most at risk of condensation.

Rule of thumb you can now defend: in Doha, outdoor air costs roughly 70–80 W per L/s to bring to room condition at the design points, before any fan energy. A 2,000 L/s fresh-air unit is a 150–170 kW coil.

Review checklist: design conditions page of any HVAC calculation

Self-check

  1. A designer states the fresh-air coil load was computed at 47 °C DB / 30 °C WB "because it is the design ambient". Write the one-sentence comment.

  2. Air leaves a cooling coil at 12 °C saturated and is reheated to 20 °C. What are its RH and humidity ratio after reheat, approximately?

  3. Why is RH the wrong quantity to write on a duct in a schematic?

  4. Doha's 0.4 % dew point is about 30 °C. What thickness question does that decide?

  5. Convert: 350 kW of cooling in tons of refrigeration; 2,500 L/s in cfm; 0.8 Pa/m in inches of water per 100 ft.

  6. What does the QCS "100 % design humidity" statement govern, and what must it never be used for?

Flashcards

Next: Module 2, cooling-load calculation and HAP review.

Week 1 · Module 2 · about 3.5 hours

Cooling-load calculation and the HAP report

A load calculation is a chain of assumptions with arithmetic at the end. Software gets the arithmetic right; reviewers earn their keep on the assumptions. This module teaches the load components, where each assumption is pinned in the design basis, and the eleven inputs you must see in a Carrier HAP report before you look at a single result.

Why it matters

Oversizing is the quiet failure. A split unit sized 40 % high cycles, never runs long enough to dehumidify, and delivers a cold, clammy room at 60 % RH. Undersizing is the loud one: the mess hall never reaches 23 °C on a July lunchtime. Both start in the same place: an envelope value, an occupancy density, a safety factor.

Concept

The load components, in the order they appear in a report

  1. Conduction through opaque envelope: q = U × A × ΔTeff. In a manual method ΔTeff is the CLTD (cooling load temperature difference), which folds in solar absorption and thermal lag; in HAP the same physics is done hour by hour with transfer functions. The U-value is the reviewer's lever.
  2. Glazing: conduction (U × A × ΔT) plus solar (A × SC × SHGF, or A × SHGC × incident irradiance in modern form). The shading coefficient is the second big lever; SC 0.3 is a high-performance glass and must appear on the architectural glazing schedule, not only in the HVAC model.
  3. People: sensible and latent per person by activity (ASHRAE Fundamentals 2021 Table 1, tabulated at 23.9 °C room; at 26.7 °C the sensible share falls about 20 % and latent rises). Occupancy count comes from the architect or, failing that, ASHRAE 62.1 default densities.
  4. Lighting: W/m² × area × usage; add a ballast/driver allowance for fluorescent (1.2) but not for LED with integral drivers if the nameplate is system watts.
  5. Equipment and small power: nameplate is not heat gain. ASHRAE gives office load densities of 5.4 / 10.8 / 16 / 21.5 W/m² for light / medium / medium-heavy / heavy workstation densities; kitchens and laundries use appliance tables with radiant and usage factors.
  6. Ventilation (outdoor air): computed at the outdoor design state chosen for it (Module 1); counted at the coil, not in the room, when the fresh air is treated centrally.
  7. Infiltration: air changes through cracks and door openings; sensible and latent. In a positively pressurised building it is normally zero except at ground floor and entrances; where a building is not pressurised, a stated ACH applies.
  8. System gains: fan heat (draw-through adds to the coil, blow-through adds to the supply), duct gains in hot ceilings and roofs, return plenum gains from recessed luminaires.
  9. Safety factor: applied last, once, explicitly.

Peak, block and diversity

Each room peaks at a different hour: east rooms at 09:00, west rooms at 16:00, the mess hall at 13:00. The sum of room peaks sizes the terminal units. The block load, the largest simultaneous total, sizes the plant that serves them. For VRF this is exactly why a connection ratio above 100 % is permitted: the outdoor unit is sized to the block, the indoor units to their own peaks. A report that sizes an outdoor unit on the sum of indoor peaks is safe but wasteful; a report that sizes indoor units on a diversified block is wrong.

Method lineage: which engine is in the software

MethodWhere you meet itStatusReviewer note
CLTD / SCL / CLF1997 ASHRAE Fundamentals Ch. 28; PDH M196; Castillo Part 1; most hand calculationsWithdrawn by ASHRAE after 2001; still valid physicsTables are at 40° N; Doha is 25° N. Month and latitude corrections must be shown.
Transfer Function Method (TFM)Carrier HAP 4.x ("ASHRAE Transfer Function Method")Superseded in the Handbook but the engine of the tool on this projectResults depend on wall/roof "groups" or layer-by-layer libraries; check the library entries match the architectural build-ups.
Radiant Time Series (RTS) / Heat BalanceASHRAE Fundamentals 2005 onward; Mitsubishi Thermal Load Estimate; HAP 5/6; IES, TRACE 3D+Current ASHRAE methodSensitive to internal mass and carpet assumptions; otherwise within a few percent of TFM for ordinary buildings.

Method differences are small compared with input errors. Do not spend review time arguing TFM versus RTS; spend it on U-values, occupancy, schedules and the outdoor-air basis.

Sanity yardsticks

ASHRAE design manual, temperate offices12 ± 3 m²/kW450 ± 100 ft²/ton, lights 16 W/m², plug 21 W/m², 14 m²/person
Gulf practice, conditioned occupied space with fresh air5 – 8 m²/kW≈ 125–200 W/m²; lower for top-floor west rooms, kitchens, gyms. Experience band, not a code value.
Supply air, all-air systems≈ 54 L/s per kW400 cfm/ton; 3–4 L/s·m² for offices
Outdoor air cost in Doha70 – 80 W per L/sFrom Module 1 at the two design basis design points

Use the bands to spot outliers, then trace the outlier to its input. A bedroom at 3 m²/kW is not "wrong"; it is asking you to look at its roof and its infiltration.

Read

  • A
    PDH M196 "HVAC Made Easy" — Parts 1–8: the clearest narrative of every component; the CLTD correction formula; the ballast factor 1.18–1.30; occupant gains by activity; supply-air CFM from sensible load. Imperial units, 1997 tables. Read for structure.
  • B
    1997 ASHRAE Fundamentals Ch. 28 (SI) — Table 3 occupant gains (SI), Table 9 office equipment densities (9–13 W/m² general, up to 47 W/m² with terminals), meal heat 15 W (75 % sensible), roof and wall group tables, the CLTD/CLF and TFM procedures with worked examples.
  • C
    Castillo Part 1, manual cooling load and Part 2, HAP workflow — the same 34.4 m² Dubai room done by hand (3.41 kW total, 2.85 sensible) and then in HAP: weather, libraries, spaces, systems, reports. The HAP deck names the inputs you should ask to see; its instruction "use HAP default if no local data" is the review red flag.
  • D
    ASHRAE Air-Conditioning System Design Manual — Table 2-1 schematic-design yardsticks (m²/kW, L/s·m², W/m²), the note that latent infiltration is substantial in hot-humid climates, and the reminder that equipment averages 50–85 % of capacity in service.
  • E
    BR 443:2006 Conventions for U-value calculations with Calculating U-values and Building materials properties — surface resistances (Rsi 0.13 / 0.10 / 0.17, Rse 0.04), bridging corrections, and the λ table you need to rebuild an architect's U-value by hand. UK heating-climate conventions: use the arithmetic, not the moisture assumptions.
  • F
    CIBSE TM37 Appendix A — casual gains by space type (cellular office 9.5 W/m² equipment, 18.8 lighting; industrial process 50 / 37.5; warehouse 2 / 11.3). Sensible-only, UK July values; use for equipment densities, never for latent.
  • G
    Infiltration sheet (CIBSE Guide A Tables 4.15 / 4.17) — offices < 2000 m² 0.4 ACH, workshops 0.3–0.5 ACH, "corrected" to half. The halving is asserted, not justified; the design basis's 1 ACH for unpressurised spaces is the governing number here.
  • H
    Mitsubishi Thermal Load Estimate v1.10 manual — a vendor RTS tool with a 20 % safety-factor floor "not to be lowered" and roof area assumed equal to floor area. If any split or VRF selection arrives from this tool, those two assumptions are your first two questions.

Qatar rules that touch this module

  • Partial
    Kahramaa Energy & Water Conservation Code (2016; 2025 re-issue CN-CNT-P2-C2 Issue 2) — loads by "engineering standards and handbooks acceptable to the Kahramaa Engineer" or ASHRAE-certified software; a cooling-load summary sheet and cooling-equipment schedule are submitted to the Kahramaa Engineer with the building permit; envelope U-values calculated for summer per ASHRAE and manufacturer-certified; wall limit 0.568 W/m²K. Roof and glazing limits to be confirmed from the code PDF.
  • Verified
    QCS 2014 Section 15 Insulation of Buildings; Section 14 Part 4 roof insulation — material and installation requirements behind the U-values; the Kahramaa insulation approval references them.
  • Verified
    GSAS 2019 D&B criteria E.1 Thermal Energy Demand Performance, E.2 Energy Use Performance — the same envelope and internal-gain inputs feed the GSAS energy model; a 16 W/m² lighting assumption in HAP and a 6 W/m² assumption in the GSAS model is an inconsistency the certifier will find.
  • Verified
    Dubai GBR 501.03 — safety factor no greater than 10 % sensible / 5 % latent; loads at the hour of peak incidence in each space. Benchmark only.

Worked example: a top-floor worker bedroom by hand

Assumptions (illustrative; the designer's model will differ): 14 m² room, 3.0 m high, one west wall 11.2 m² gross with a 1.5 m² window, roof above; room 22 °C / 50 %; ambient 47 °C / 30 °C WB; not pressurised (toilet extract drives infiltration), so 1 ACH applies; two occupants seated at rest; design basis Tables 4-2 and 4-4 values.

1
Wall 0.568 × 9.7 m² × (25 K + 6 K solar allowance) = 171 W. (A CLTD table or HAP replaces the 6 K allowance with an hourly value.)
2
Roof 0.437 × 14 × (25 + 15 K sol-air allowance) = 245 W. The roof is the largest envelope item even at U = 0.437; at U = 0.3 it would be 168 W.
3
Glazing conduction 3.3 × 1.5 × 25 = 124 W; solar 1.5 × 0.3 × 560 W/m² (west peak irradiance, illustrative) = 252 W. With SC 0.6 the solar term doubles.
4
People 2 × 70 = 140 W sensible, 2 × 45 = 90 W latent. Lighting 16 × 14 = 224 W. Small power 200 W.
5
Infiltration 1 ACH of 42 m³ = 11.7 L/s. Sensible 1.2 × 0.0117 × 25 = 350 W; latent 3010 × 11.7 × (0.0199 − 0.0082) / 1000 = 410 W.
6
Sum: sensible 1,706 W; latent 500 W; total 2,206 W. Infiltration is 34 % of the room load. Apply Table 4-3 as 10 % on sensible and latent: 1,877 + 550 = 2,427 W; if the 20 % total is compounded on top, 2,910 W.
Result: about 2.4–2.9 kW (0.7–0.8 TR), i.e. 170–210 W/m² or 4.8–5.8 m²/kW. A 2.6 kW (9,000 Btu/h) hi-wall unit is plausible; a 3.5 kW unit is oversizing driven by the compounded factor. Sensible-heat ratio 0.77: an ordinary split can hold it, but only while it runs; the latent 500 W returns the moment the compressor cycles off.

The 55 L/s question. Table 4-1 lists "55 LPS" as the ventilation rate for each accommodation prototype. Applied per bedroom as outdoor air it would add about 4.5 kW at the 34/32 condition, more than the whole room load, and no hi-wall split could treat it. It can only be a toilet-extract rate per unit or a per-floor figure. Ask the designer to state the basis and the resulting infiltration path; then check that the corridor is not being pulled negative against the stair.

Review checklist: HAP report (or any load calculation)

Self-check

  1. A HAP report shows a 60 m² admin office at 14.2 kW (4.2 m²/kW). Which three inputs do you open first?

  2. The designer applied HAP's 10 % sensible and 10 % latent sizing factors and then multiplied the schedule by 1.2 "per Table 4-3". What is the resulting margin and what do you write?

  3. Why does the block load, not the sum of zone peaks, size a VRF outdoor unit, and what design basis number depends on that?

  4. Occupant gains in Annex A are tabulated at 23.9 °C. The mess hall is designed at 23 °C, the pump room at 24 °C. Does it matter?

  5. A wall build-up gives U = 0.52 W/m²K in the architect's calculation and 0.568 in the HAP model. Which is the review issue?

  6. Name two loads the design basis explicitly deferred and what you should demand before accepting the mess hall and laundry load calculations.

Flashcards

Next: Module 3, ventilation, filtration and pressurisation.

Week 1 · Module 3 · about 2.5 hours

Ventilation, indoor air quality, filtration and pressurisation

Fresh air is the most expensive air on the site and the least visible on a drawing. This module gives you the ASHRAE 62.1 arithmetic, the exhaust rates, the pressure relationships that keep toilets and kitchens from flavouring the corridors, and the sand and salt defences that a coastal desert demands.

Why it matters

Three separate "air changes per hour" appear in a Gulf design basis and they are not the same quantity: outdoor air for people, exhaust for contaminant removal, and supply for pressurisation or heat removal. Designers and reviewers talking past each other on which ACH is meant is the most common source of a wrong fan, a wrong coil and a negative-pressure building that pulls hot wet air through every door.

Concept

ASHRAE 62.1 Ventilation Rate Procedure

V_bz = R_p × P_z + R_a × A_z V_oz = V_bz / E_z (E_z = 1.0 ceiling supply of cool air; 0.8 for some displacement/underfloor cases)

Rp is a per-person rate, Ra a per-area rate; both are additive because people and materials each emit. The breathing-zone quantity Vbz is divided by the zone air-distribution effectiveness to give the outdoor air the diffusers must deliver. For a multi-zone recirculating system a further system efficiency applies (Appendix A of the standard); for dedicated treated-fresh-air units serving each space directly, Voz is what the TFAHU must deliver to that room.

Occupancy category (62.1-2022 Table 6-1)Rp L/s·personRa L/s·m²Default density per 100 m²Air class
Office space2.50.351
Reception areas2.50.3301
Lobbies (public assembly)2.50.31501
Places of religious worship2.50.31201
Restaurant / dining rooms3.80.9702
Supermarket3.80.381
Retail sales3.80.6152
Gym, sports arena (play area)100.972
Health club / weight rooms100.3102
Residential dwelling unit (bedrooms + 1 occupants)2.50.31
Common corridors (residential)0.31
Warehouses5.00.322
General manufacturing / workshop5.00.960 / 203 / 2
Rows transcribed from the 62.1-2022 extract reproduced as Annex A Table 3-8 of the design basis (page 93) and from 62.1-2013 in the library; check the exact row for each space against the standard before quoting. Electrical rooms, substations and battery rooms have no 62.1 row: their air is set by heat removal and safety rules, not by people.

Exhaust rates (62.1-2022 Table 6-2, Annex A Table 3-9)

Toilets private 12.5/25 L/s per fixture, public 25/35 L/s per fixture; shower rooms 10/25 L/s per showerhead; commercial kitchens 3.5 L/s·m² (the hood calculation governs in practice); kitchenettes 1.5; janitor and trash rooms 5.0 (Class 3, no recirculation); soiled laundry storage 5.0 (Class 3); locker rooms 1.25–2.5; parking 3.7 L/s·m². Where a prescriptive ACH and a per-fixture rate both exist, the larger governs and the drawing must say which was used.

Pressure relationships: the map, not the number

Air moves from high pressure to low. Draw the building as a set of boxes with arrows: fresh air in, exhaust out, and net flow at every door. Clean spaces sit at the top of the cascade (positive), corridors below them, toilets, kitchens and laundries at the bottom (negative). The quantities that produce the cascade are small: 5–12 Pa positive across the envelope is enough to stop infiltration in an ordinary building; 25 Pa is the IEC 60079-13 minimum for a pressurised room in a hazardous area; 50 Pa is a smoke-control or process-plant figure that costs door-opening force (about 47 N on a standard door, within the 133 N limit of NFPA 101 but noticeable) and requires airlocks.

The supply needed to hold a pressure is a leakage calculation (the "crack method"): sum the leakage areas of doors, windows and penetrations and apply Q = C × A × ΔPn. BS 5588 Part 4 used to carry the tables; it is withdrawn, and BS EN 12101-6 (pressure differential systems) and ASHRAE's smoke-control handbook chapter are the current sources. A 1 ACH rule for "general buildings" is a convenient stand-in that a designer must still reconcile with the actual leakage; for a leaky warehouse it is optimistic, for a tight office it is generous.

Untreated ventilation and the moisture question

An accommodation room ventilated only by toilet extract receives its outdoor air as infiltration through window and door cracks, at outdoor humidity, straight into the room. At the 34/32 design morning that air carries 30 g/kg. The split unit must remove the difference to 8–10 g/kg while it runs and can do nothing while it cycles off. Whether the room stays below 60 % RH depends on the ratio of latent load to coil latent capacity at part load, which is exactly the analysis a moisture balance provides and a load calculation does not.

Sand, salt and filters

  • Sand-trap louvres at 1.0 m/s face velocity on gross area, at every intake, with a washable metal pre-filter behind them; intakes at high level, upwind of pollution sources, and 10 m from any exhaust.
  • Filtration is specified by ASHRAE 52.2 MERV ratings (52.1 is withdrawn; a document citing both is out of date on one of them). MERV 7–9 panel or bag filters as pre-filters, MERV 13 on treated-fresh-air units; ISO 16890 is the equivalent European ladder (ePM10, ePM2.5, ePM1) you will see on European datasheets.
  • Differential-pressure switches or sensors across every filter bank, reported to the BMS, per QCS Section 22.
  • Energy recovery on treated fresh air: plate or wheel; effectiveness stated as sensible or total (enthalpy); an "80 % minimum efficiency" requirement needs to say which. Kitchen exhaust (Class 3) is never recovered through a wheel that can leak into supply.

Read

  • A
    ANSI/ASHRAE 62.1-2013 (reduced) — §6.2 Ventilation Rate Procedure, Table 6.2.2.1 rates, Table 6.5 exhaust rates, §5.9.2 (outdoor-air intake must equal or exceed maximum exhaust), §5.16 air classes and recirculation limits, §6.4 natural ventilation procedure. The project cites the 2022 edition; the structure is the same and the design basis Annex A reproduces the 2022 tables.
  • B
    HVAC Design Guidelines (corporate extract) — the requirement for a ventilation schedule and an air-balance schedule on the drawings (room, function, occupants, rate, method, subtotals, pressurisation). Adopt that expectation for every building here; it is the fastest way to audit a pressure cascade.
  • C
    ASHRAE Design Manual — intake louvre face velocities (3.3 m/s on net free area for ordinary louvres; the Gulf sand-trap figure of 1 m/s is far lower by design), exhaust louvres 7.6 m/s, and the note on latent infiltration in hot-humid climates.
  • D
    PDH M196 Part 7 — infiltration through open doors (velocity ∝ √height × √ΔT; a 2.4 × 1.2 m door at 100 °F ΔT passes about 1 m³/s while open), which is why mess-hall and laundry entrances need vestibules or air curtains in this climate.

Qatar rules that touch this module

  • Partial
    QCS 2014 Section 22 Part 4 Air Handling Equipment (filters clause cited as 4.6) and Part 1 — filter classes, differential-pressure indication, sand-trap louvres and screens on all inlets. Clause text to be confirmed from the Section 22 PDF.
  • Verified
    GSAS 2019 IE.3 Mechanical Ventilation, IE.2 Natural Ventilation — credits for exceeding 62.1 rates and for CO2 monitoring; the design basis's "no more than 20 % above 62.1" caps the credit path, so the GSAS strategy and the design basis rule must be reconciled.
  • Partial
    QCDD 2015 annex ACMV_N1 and the 2022 Technical Requirements Guide — mechanical ventilation and smoke-control notes; pressurisation of protected stairs and lobbies (FLS_A2); DC2 approval. Numeric criteria inside ACMV_N1 to be confirmed from the document.
  • Verified
    BS EN 12101-6 (pressure differential systems) and NFPA 92 — the current homes of the leakage ("crack") method and stair pressurisation criteria (NFPA 92: 12.4 Pa sprinklered / 24.9 Pa unsprinklered minimum across a closed stair door; BS EN 12101-6: 50 Pa class systems). BS 5588 Part 4 is withdrawn.
  • Verified
    IEC 60079-13 and NFPA 496 — 25 Pa minimum overpressure for pressurised rooms in classified areas; not applicable to an accommodation project, but the origin of the "+50 Pa" rows in the design basis template.

ASHRAE 62.1 Ventilation Rate Procedure and the 1 ACH rule

Defaults are a 600 m² mess hall (dining rooms row), 420 seats, 4.5 m high. Change the rates for other rows.

Vbz L/s
Voz = Vbz/Ez L/s
1 ACH equivalent L/s
Governing minimum L/s
design basis cap (+20 %) L/s
62.1 rate as ACH ACH

Worked example: mess hall fresh air and the treated-fresh-air unit

1
Dining rooms: Vbz = 3.8 × 420 + 0.9 × 600 = 1,596 + 540 = 2,136 L/s. With Ez = 1.0, Voz = 2,136 L/s. The 1 ACH rule gives 2,700 m³/h = 750 L/s, so 62.1 governs. The design basis cap is 1.2 × 2,136 = 2,563 L/s.
2
Coil load bringing 2,136 L/s from 34 °C / 32 °C WB to 20 °C / 50 %: 1.2 × 2.136 × (110.5 − 38.6) = 184 kW (52 TR). At 47/30 it would be 154 kW; the difference is why the design basis's outside-air basis exists.
3
Fan power limit 1.75 W per L/s → 3.7 kW for the TFAHU supply fan; check the fan curve at the design external static, not the motor nameplate.
4
Energy recovery: a wheel or plate on the dining relief air (Class 2) can pre-cool the fresh air; the kitchen hood exhaust (Class 3, grease) cannot pass through it. An 80 % "efficiency" claim must name sensible or total effectiveness and the exhaust quantity it is based on; with only part of the supply matched by recoverable exhaust, the recovered duty is smaller than the headline.
5
Pressure: supply 2,136 L/s of fresh air; kitchen hood exhaust (say 3,500 L/s, from the hood calculation) is served by its own make-up air unit; dining exhaust set about 10 % below the fresh air so the hall stays positive to the kitchen and the outside. Show all three on an air-balance schedule.
One dining hall drives a 52 TR fresh-air coil, a 3.7 kW fan, and a three-way air balance. CO2 demand control (design basis) reduces the energy, not the installed size; the sizing case is the full Friday sitting.

Review checklist: ventilation and pressurisation submittals

Self-check

  1. A drawing states "Substation: 10 ACH". List the three questions that decide whether the fan and coil are right.

  2. Compute Vbz for a 150 m² prayer hall at the 62.1 default density.

  3. Why must outdoor-air intake equal or exceed the maximum exhaust, and which clause says so?

  4. The TFAHU datasheet quotes "heat recovery efficiency 80 %". What two words are missing?

  5. What is wrong with citing "ASHRAE 52.2-1999" and "ASHRAE 52.1" in the same specification?

  6. Explain to a client in two sentences why "+50 Pa" for a substation in an accommodation project should be questioned.

Flashcards

End of Week 1. Next: Module 4, system selection and VRF.

Week 2 · Module 4 · about 2 hours

System selection and the VRF decision

Which system serves which building is a decision already made in the design basis; your job is to see that detailed design honours it, that the physical limits of the chosen system are respected on every drawing, and that the coastal environment has been designed for rather than merely mentioned.

Why it matters

Variable-refrigerant-flow systems fail in predictable ways on large sites: refrigerant runs stretched past the manufacturer's limits, outdoor units starved on a roof of other outdoor units' discharge, connection ratios pushed to the maximum and then the capacity at 47 °C forgotten, and a refrigerant charge large enough that a leak into the smallest bedroom on the circuit breaches the concentration limit. None of these appear in a load calculation. All of them appear on layout drawings and schedules, which is where you will meet them.

Concept

The system families and what each buys you

SystemWhere it fitsStrengthsReview hazards in Qatar
DX split (hi-wall, floor, ducted)Small rooms, guardhouses, pump rooms, standalone spacesSimple, cheap, room-by-roomCondensing units at 47 °C; no fresh-air path; condensate from many small units; nuisance oversizing
VRF / VRV (heat-pump or heat-recovery)Accommodation, offices, clinics, retail, clubhousesZone control, part-load efficiency, long refrigerant runs, one roof plant per buildingPiping length and level limits; capacity at high ambient and at high connection ratio; refrigerant concentration in small rooms; roof recirculation; BMS integration only through gateways
Rooftop packaged DXMosques, mess halls, laundries, workshops, substationsFresh air and filtration in one box; robust; serviceable outsideDerating at 47–52 °C; duct runs across hot roofs; sand loading on condensers; noise to neighbours
Chilled water (air-cooled chillers or district cooling)Large campuses, hospitals, towersCentral plant efficiency, water not refrigerant in occupied spaceRejected for this project in the cooling comparison study; potable water banned for cooling towers in Qatar since 2014, so water-cooled means TSE
Treated fresh-air units (TFAHU / FAHU), energy-recovery units, make-up air units, ecology unitsAny building with central fresh air; kitchensDecouple latent load from room units; recover exhaust energy; clean kitchen exhaustCoil selection at 34/32; wheel effectiveness claims; Class 3 exhaust never recovered; ecology unit pressure drop and maintenance access

How a VRF system works, in the terms a datasheet uses

One inverter-driven outdoor unit modulates compressor speed to hold a target refrigerant pressure; each indoor unit has an electronic expansion valve controlled from its own coil thermistors, so it takes only the refrigerant it needs. Capacity therefore follows the sum of indoor-unit demands up to the outdoor unit's limit. Three consequences matter for review:

  • Connection (index) ratio: total indoor capacity ÷ outdoor capacity. Manufacturers permit 50–130 % (some to 150–200 % with derating). Above 100 % the outdoor unit cannot serve all indoor units at full load simultaneously; the design must show the block load (Module 2) is within the outdoor unit's capacity at site conditions.
  • Piping geometry: total pipe length, longest actual and equivalent run, length after the first branch, level difference outdoor-to-indoor and indoor-to-indoor. Each limit exists for oil return and pressure drop; each exceedance costs capacity or triggers a manufacturer's refusal to warrant. The schedule must state the values used and the correction factor applied.
  • Refrigerant charge: a system's charge is the outdoor unit's factory charge plus a per-metre allowance for liquid line. Charges of 30–100 kg per system are ordinary. ASHRAE 15 / ISO 5149 / EN 378 limit the concentration that a full leak could produce in the smallest occupied room served: for R-410A the refrigerant concentration limit is 0.42 kg per m³ of room volume (ASHRAE 34). A 42 m³ bedroom therefore tolerates about 17 kg. Where the circuit charge exceeds that, the standards require mitigation: smaller circuits, leak detection with alarm, or safety ventilation interlocked to the detector.

Coastal-desert engineering

Salt aerosol, sand loading and ultraviolet are the three degradation drivers. The vocabulary you will see on datasheets: ISO 12944 corrosivity class C5-M (very high, marine) for paint systems, salt-spray endurance in hours per ASTM B117 / ISO 9227 (5,000 h is a heavy-duty specification), pre-coated or post-coated condenser coils (phenolic dip, epoxy electro-coat, or hydrophilic blue-fin as a light option), powder-coated casings with film thickness in micrometres, stainless fasteners, and sand-trap louvres or hoods on outdoor-unit intakes. None of these are free: coatings add condenser air-side pressure drop and reduce heat transfer a few percent, which must be in the capacity claim.

Refrigerant policy in 2026

R-410A (GWP 2,088) has zero ozone-depletion potential, which is the only environmental claim the design basis makes. Qatar is an Article 5 party to the Montreal Protocol, targets complete HCFC (R-22) phase-out by 2030, and had not ratified the Kigali Amendment as of late 2025, so there is no domestic HFC phase-down schedule yet. Lower-GWP alternatives (R-32, GWP 675; R-454B) are class A2L, mildly flammable, with additional charge-limit and ventilation rules; QCS 2014 and the QCDD 2022 guide contain no explicit A2L provisions, so any proposal to use them must be agreed with QCDD early on the basis of ASHRAE 15-2022 / ISO 5149. A reviewer's position: accept R-410A as the basis, require the refrigerant concentration checks, and record the GWP exposure in the risk register for a 25-year asset.

Read

  • A
    ASHRAE Air-Conditioning System Design Manual — Chapter 2 (the design process and system selection criteria) and Chapter 5 (components: vapour-compression cycle, coils, fans). The extract in the library ends before the all-air / all-water chapters; the selection logic is still the best short treatment.
  • B
    McQuay AG 31-011 Refrigerant Piping Design Guide — explicitly excludes VRF, but its treatment of oil return, risers, subcooling and low-ambient control is the physics behind every VRF piping limit. Read Sections 3–5.
  • C
    HVAC Design Guidelines (corporate extract) — "ease of operations, high efficiency and maintenance should be the primary focus in selecting systems"; evaluate chillers, pumps and air-handling motors for reliability and access for removal. A useful template for the questions to put to the comparison study.
  • D
    Dubai Green Building Regulations 502.01 and 502.11 — HVAC equipment efficiency tables and pipe/duct insulation to prevent condensation; regional precedent for what a "green" VRF specification contains.

Qatar rules that touch this module

  • Partial
    QCS 2014 Section 22 Part 2 (central refrigeration and AC equipment) and Part 3 (unitary equipment) — construction, corrosion protection, refrigerant safety and testing of DX and VRF equipment; Part 1 outdoor noise limit 65 dB(A) at 1 m.
  • Verified
    Ministerial directive 2013 / Kahramaa — potable water prohibited in all central cooling plants from January 2014; cooling towers on treated sewage effluent only. Relevant if any future option study revisits water-cooled plant.
  • Verified
    Law 19/2024 on district cooling and Kahramaa Decision 03/2026 — buildings inside designated district-cooling areas may be obliged to connect; a Qatar industrial city is not a designated area to public knowledge.
  • Verified
    Montreal Protocol status — Qatar HCFC phase-out by 2030 (HPMP Stage II/III); Kigali Amendment not ratified as of October 2025; no domestic rule on A2L refrigerants found.
  • Verified
    ASHRAE 15-2022 / ASHRAE 34 / ISO 5149 / EN 378 — refrigerant concentration limits (R-410A RCL 0.42 kg/m³) and mitigation requirements for occupied spaces served by large-charge systems.
  • Verified
    ISO 12944 (C5-M), ISO 9227 / ASTM B117 salt spray — the corrosion vocabulary the design basis invokes; require test certificates, not brochure statements.

Worked example: is this VRF circuit inside its limits?

A junior accommodation block, G+2, one outdoor unit per stair core on the roof serving 24 bedrooms (24 hi-wall indoor units) plus a corridor ducted unit.

1
Piping: longest actual run roof → ground-floor far bedroom 68 m, equivalent length with fittings 85 m (limit 160 / 200 m: pass); length after first branch 32 m (limit 40 m: pass); total piping 410 m (limit 1,000 m: pass); level difference ODU above IDU 11 m (limit 90 m: pass); between IDUs 7 m (limit 30–40 m: pass).
2
Connection ratio: 24 × 2.8 kW + 5.6 kW corridor = 72.8 kW indoor; outdoor unit nominal 56 kW → ratio 130 % (at the limit). Block load from HAP at 16:00 = 49 kW.
3
Capacity at site: manufacturer's curve at 47 °C ambient and indoor 22 °C / 50 % (about 16 °C WB) gives a factor of 0.86; piping correction at 85 m equivalent 0.95; connection-ratio derating at 130 % per curve 0.97. Available = 56 × 0.86 × 0.95 × 0.97 = 44.4 kW against a 49 kW block: 9 % short.
4
Refrigerant: factory charge 11.5 kg plus 410 m of liquid line at about 0.06 kg/m (9.5 mm) → roughly 36 kg. Smallest bedroom 42 m³ × 0.42 kg/m³ = 17.6 kg allowable: exceeded. Mitigation is required (smaller circuits per floor, or leak detection with alarm and ventilation per ASHRAE 15).
Two findings from one schedule: upsize the outdoor unit (or lower the connection ratio) and re-plan the circuits so that no bedroom can receive a charge above its concentration limit. Neither is visible in the load calculation.

Review checklist: system schematics and VRF schedules

Self-check

  1. A VRF schedule shows a connection ratio of 145 % "as permitted by the manufacturer". What must accompany it?

  2. Why does a refrigerant circuit's charge matter to an HVAC reviewer of an accommodation block?

  3. Name three physical reasons VRF piping has a maximum length after the first branch.

  4. The datasheet says "condenser coil: hydrophilic blue fin". Is that C5-M protection?

  5. Chilled water was rejected for the project. Which two Qatar rules would have shaped a water-cooled option?

  6. Rooftop outdoor units hidden behind a louvred parapet: what do you ask for?

Flashcards

Next: Module 5, equipment selection and datasheet review.

Week 2 · Module 5 · about 3 hours

Equipment selection and datasheet review

A datasheet is a claim made at a condition. The reviewer's whole task is to find the condition, move it to the project's, and see what survives. This module gives you the rating standards, the derating logic, the efficiency and noise rules Qatar imposes, and a datasheet checklist that fits on one screen.

Why it matters

"28 kW" on a VRF outdoor unit is its capacity at 35 °C outdoor and 27 °C / 19 °C WB indoor, which is a Tokyo afternoon, not a the site one. At 47 °C the same machine gives 80–88 % of that and draws 30–40 % more power. A schedule that lists nominal capacities against design loads is the single most common defect in Gulf HVAC submittals, and the one most likely to reach commissioning unnoticed because the arithmetic "matches".

Concept

Rating conditions you will see on datasheets

StandardApplies toOutdoorIndoor (return air)Note
ISO 5151 / GSO 5151 / EN 14511 "T1"Unitary and split air conditioners35 °C DB / 24 °C WB27 °C DB / 19 °C WBThe basis of most catalogue capacities and of Kahramaa's T1 EER
ISO 5151 "T3"Hot-climate rating46 °C DB / 24 °C WB29 °C DB / 19 °C WBThe Gulf rating; Kahramaa's T3 EER; QS 2663 star rating test
AHRI 210/240, 340/360, 390Unitary DX by size class35 °C26.7 °C / 19.4 °C WBKahramaa 2016 packaged-unit table cites these (EER 9.0 / 8.9 / 8.6 by size)
AHRI 1230VRF multi-split35 °C26.7 °C / 19.4 °C WBIEER for part-load; VRF catalogue tables usually show 35 °C and a derating chart to 52 °C
AHRI 550/590Chillers35 °C (air-cooled)6.7 °C leaving waterKahramaa 2016 chiller COP/IPLV table
AHRI 430 / 410, EN 1216Air-handling units and coilsStated entering air and refrigerant/water conditionsCoil capacity is only meaningful with the entering DB/WB printed beside it

Moving the claim to site conditions

Air-cooled DX capacity falls roughly 1 % per kelvin of condenser entering air above 35 °C and input power rises 2–3 % per kelvin; at 47 °C expect 85–90 % capacity and 125–135 % power, so EER falls by about a third. Indoor entering wet-bulb moves capacity the other way: at 22 °C / 50 % (about 16 °C WB) the coil sees a lower wet-bulb than the 19 °C rating and delivers less total capacity but a higher sensible fraction. Only the manufacturer's selection software or published correction tables give the exact factors; a datasheet without them is incomplete. Add screen or parapet recirculation (Module 4) to the entering-air temperature before reading the curve.

Efficiency metrics and which one Qatar asks for

  • EER (Btu/h per W) or COP (W/W; EER = 3.412 × COP) at full load and a stated condition. Kahramaa's tables are EER at T1 and T3 for room and split units, EER at 35 °C for packaged units, COP and IPLV for chillers.
  • IEER / IPLV / SEER: part-load weighted metrics. ASHRAE 90.1 Table 6.8.1 uses IEER for unitary and VRF above 19 kW; Kahramaa's 2025 code points to ASHRAE 90.1 Table 6.8.1-3 for chillers.
  • Star rating (QS 2663, Kahramaa/Tarsheed): mandatory label for unitary air conditioners up to about 70,000 Btu/h sold in Qatar; minimum 3 stars, tested at T3. A VRF outdoor unit or a packaged rooftop unit above the scope has no star rating; asking for one is a category error, and the applicable instrument is the Kahramaa code table or ASHRAE 90.1.

Noise: from a datasheet number to a bedroom

Datasheets quote sound power (Lw, dB(A) re 1 pW) or sound pressure at a distance (Lp at 1 m). For a unit on a flat roof radiating into a hemisphere, Lp ≈ Lw − 20 log10(r) − 8, so 80 dB(A) sound power is about 72 dB(A) at 1 m and 52 dB(A) at 10 m, before barriers or multiple units (+3 dB per doubling of units). QCS caps outdoor equipment at 65 dB(A) at 1 m. Indoor criteria are in NR (design basis: NR 30 bedrooms and mosques, NR 35 offices and clinic, NR 40 halls, retail, workshops); an NR value is a spectrum, and the datasheet must give octave-band sound power for the acoustic consultant to check it. NC (North American) and NR (ISO) are numerically close but not identical; use one in the specification.

Electrical and controls data the mechanical reviewer still owns

Qatar supply is 415/240 V, three-phase four-wire, 50 Hz; Kahramaa requires the AC load to be declared with the building permit and a power factor of 0.9 or better. A datasheet must give full-load and maximum current, starting current or inrush (inverter units are soft), IP rating of outdoor electrical enclosures (design basis: IP55 inside, IP64 outside; QCS/Shell-based fire-system tables go to IP66 outdoors), motor efficiency class (IE2 minimum per the Kahramaa 2023 code snippet; IE3 is the safer specification), and the control interface (BACnet gateway for VRF, hard-wired points for packaged units).

The vendor-document review cycle

Datasheets arrive with a review code convention: typically Code 1 no comments, Code 2 proceed with comments incorporated, Code 3 revise and resubmit, Code 4 rejected or for information. Your comment must be resolvable: name the design basis or specification clause, the datasheet field, and the acceptable evidence (a curve, a certificate, a corrected value). A technical bid evaluation is the same exercise done line by line in a compliance matrix, with commercial weighting kept separate from technical compliance.

Read

  • A
    Recommended Noise Criterion (NC / NR sheet) — NR by room type (dwellings and hospitals NR 30, offices NR 35–40, canteens NR 45, light engineering NR 60), crosstalk attenuator rules (≤ 1.5 m/s, ≤ 10 Pa) and attenuator length versus insertion loss (600 mm ≈ 22 dB, 900 mm ≈ 28 dB, 1,250 mm ≈ 34 dB).
  • B
    ASHRAE Design Manual Chapter 5 — components and the part-load reality check (cooling equipment averages 50–85 % of capacity in service): the argument for IEER over EER.
  • C
    Dubai Green Building Regulations 502.01 — HVAC equipment minimum efficiency reference tables; the closest published regional analogue to the Kahramaa tables for cross-checking a vendor's claim.
  • D
    Mitsubishi Thermal Load Estimate manual — shows how a vendor selection tool is chained to the load estimate (export to the design tool); when a vendor "selects" equipment from its own load tool, the 20 % floor and the weather city chosen are inherited into the selection.

Qatar rules that touch this module

  • Verified
    QS 2663 (Qatar adoption of SASO 2663) and the Kahramaa/Tarsheed star-rating programme — mandatory energy label for unitary air conditioners; non-compliant units banned from import and sale since July 2016; minimum 3 stars (EER 8.5 window / 9.5 split at the 2013 announcement; the 2016 code table gives 11.5 T1 / 8.28 T3 for splits). Scope up to about 70,000 Btu/h.
  • Partial
    Kahramaa Energy & Water Conservation Code 2016 → 2023 (CN-CNT-P2/C1) → 2025 (CN-CNT-P2-C2 Issue 2) — equipment efficiency tables; chillers per ASHRAE 90.1 Table 6.8.1-3; unlisted equipment per ASHRAE 90.1 §6.4.1; polyphase motors IE2 minimum (2023 snippet); cooling-equipment schedule submitted with the permit.
  • Verified
    Kahramaa Electricity Wiring Code 2018 (CS-CSI-P1/C1) — 415/240 V, 3-phase 4-wire, 50 Hz; AC loads calculated and submitted with the permit; connected and diversified load per distribution board; power factor 0.9 lagging or better.
  • Partial
    QCS 2014 Section 22 Part 1 — outdoor equipment noise not to exceed 65 dB(A) at 1 m; Part 9 sound and vibration control (silencers, anti-vibration mounts); Part 3 unitary equipment.
  • Verified
    ASHRAE 90.1-2019/2022 Table 6.8.1 — minimum IEER/EER for unitary and VRF equipment by size class; the reference GSAS E.2 modelling uses as a baseline.

Worked example: reading a packaged rooftop unit datasheet for a daily mosque

1
Load from HAP: prayer hall block 68 kW total, 52 kW sensible (SHR 0.76) at 22 °C / 50 %, with 1,100 L/s fresh air already inside the load at 34/32.
2
Datasheet: "Nominal cooling 75 kW (AHRI 340/360)". At 47 °C entering condenser air the vendor's table gives 0.87 → 65 kW total; at the entering coil condition of 26 °C / 18 °C WB (mixed air with 1,100 L/s of 34/32 fresh air) sensible capacity reads 47 kW.
3
Verdict on capacity: 65 < 68 kW total and 47 < 52 kW sensible: the unit is short on both, by 4 % and 10 %. Nominal 75 kW "covered" a 68 kW load only at 35 °C.
4
Efficiency: EER 9.4 at 35 °C against the Kahramaa 2016 minimum 8.6 for ≥ 39.56 kW (AHRI 390): compliant at rating, but the site EER at 47 °C will be near 6.5; record both.
5
Noise: sound power 88 dB(A) → about 80 dB(A) at 1 m, exceeding the QCS 65 dB(A) limit; discharge attenuators or a low-noise fan option are needed, and the NR 30 hall requires octave-band data on the supply duct plus lined duct or silencers.
6
Electrical and environment: 415 V / 50 Hz stated; FLA 42 A, starting current given; IP55 control box (design basis wants IP64 outdoors: comment); condenser coil "epoxy coated, 1,000 h salt spray" against the design basis's 5,000 h: comment.
Code 3, revise and resubmit: capacity at 47 °C and at the mixed entering condition; sound power spectrum and attenuation; IP64 outdoor enclosures; 5,000 h salt-spray evidence. Each comment names the design basis clause and the field to change.

Review checklist: any HVAC equipment datasheet or schedule

Self-check

  1. A split unit datasheet shows EER 12.0. Which rating condition must you confirm before comparing it with Kahramaa's table?

  2. Convert sound power 85 dB(A) to sound pressure at 3 m for a roof-mounted unit, and state the QCS reference point.

  3. Why is IEER a better criterion than EER for a VRF serving a clubhouse?

  4. The schedule lists "capacity 10 kW at 52 °C". What is wrong with the sentence?

  5. What evidence closes a comment on "5,000 h salt spray"?

  6. Which reviewer, mechanical or electrical, owns the power-factor and IP-rating lines on an HVAC datasheet?

Flashcards

Next: Module 6, ducts, outlets, insulation and dampers.

Week 2 · Module 6 · about 2.5 hours

Air distribution: ducts, outlets, insulation and dampers

Duct drawings are where a design becomes buildable and where most site queries originate. This module covers the equal-friction method the design basis prescribes, the velocity and pressure-drop limits it fixes, the construction standard question (DW/144 or SMACNA), condensation-driven insulation, and the dampers that fire safety and the client's philosophy require.

Why it matters

An undersized duct is quiet on paper and loud in the mosque. An unspecified leakage class turns into 15 % of the fan's air heating the ceiling void. Insulation chosen from an energy table sweats onto a false ceiling in September. And a missing fire damper is a Civil Defence rejection at DC2 with the ceiling already closed. Every one of these is visible on a well-prepared duct drawing and invisible on a poor one, so the review starts by checking that the drawing carries the information at all.

Concept

Equal friction: the method and its two dials

Choose a friction rate (Pa per metre of duct) and size every section so that its friction loss equals that rate; the duct gets larger as the air quantity grows. The method is simple and self-balancing enough for low-pressure systems. Its dials are the friction rate and a velocity ceiling: the friction rate sets fan energy and duct size, the velocity ceiling sets noise. A design basis usually fixes both by system type, as this one does in Table 4-7 (AHU supply 0.6 Pa/m and 7.6 m/s; return 0.5 Pa/m and 6.1 m/s; FCU ducts 0.4 Pa/m and 4.5 m/s; extract and fresh-air units 0.8 Pa/m and 9.1 m/s; smoke extract 1.2 Pa/m and 10 m/s). The duct-sizing chart in your library from another Gulf project uses 1.25 Pa/m, which shows how project-specific the number is.

Round ducts carry the chart; rectangular ducts are converted by the Huebscher equivalent diameter, De = 1.30 (ab)0.625 / (a + b)0.25, which gives the rectangular size with the same friction at the same airflow. Keep aspect ratios at or below 4:1; beyond that the sheet metal cost and leakage climb faster than the space saved.

Acoustic velocity limits are separate from friction limits

ASHRAE HVAC Applications (reproduced in the design basis as Figure 4-2 and Annex A Table 3-10) caps main-duct velocity by the room criterion and the duct location: for RC/NR 25 rooms, 4.8 m/s for rectangular duct within the occupied space, 6.1 m/s above a suspended acoustic ceiling, 8.6 m/s in a shaft; for RC/NR 35 the corresponding figures are 7.4, 8.9 and 12.7 m/s. Branches run at about 80 % and final run-outs at 50 % or less of the main-duct values. Supply outlets: 1.8 / 2.2 / 2.5 / 2.8 m/s "free" opening velocity for RC 25 / 30 / 35 / 40; returns 2.2 / 2.5 / 3.0 / 3.4 m/s. A bedroom at NR 30 with a supply diffuser at 2.5 m/s is over the acoustic limit before any duct noise arrives.

External static pressure is a sum, and the fan is selected on it

ESP = straight-duct friction + fitting losses (loss coefficients, ASHRAE Duct Fitting Database) + terminal devices + volume dampers + filters at their dirty pressure drop + coils + louvres + attenuators, on the supply and the return path, plus system effect at the fan. Fan-coil units are sold in low (30–50 Pa), medium (80–120 Pa) and high (150–250 Pa) static families; a duct calculation that comes out at 120 Pa against a 50 Pa unit has selected the wrong family, and the site symptom is a starved far diffuser.

Construction standard: pressure class, gauge, sealing, leakage

ItemDW/144 (BESA, UK)SMACNA HVAC Duct Construction Standards (US)
Pressure classesLow (to 500 Pa), medium (to 1,000 Pa), high (to 2,000 / 2,500 Pa)½, 1, 2, 3, 4, 6, 10 in. w.g. (125 Pa to 2.5 kPa)
Leakage classesA, B, C: 0.027 / 0.009 / 0.003 × p0.65 L/s per m² of duct surfaceLeakage classes 3, 6, 12, 24, 48 cfm per 100 ft² at 1 in. w.g.; seal classes A, B, C by pressure class
Leakage testingDW/143; high-pressure ductwork tested, low-pressure sampledSMACNA leakage test manual; tests as specified
Gauge and stiffeningTables by longest side and pressure classTables by longest side, pressure class and reinforcement spacing
MaterialHot-dip galvanised to BS EN 10346 (formerly BS 2989 Z2 in QCS text)G90 (Z275) galvanised

Either standard is acceptable; a specification must name one and its edition, because gauge tables, joint types and leakage classes do not map one to one. QCS 2014 Section 22 Part 6 allows ASHRAE/SMACNA fabrication with DW/144 for BS-familiar contractors; your job is to see that the drawing set, the specification and the test method all say the same thing. A drawing note "DW-142" is a 1980s reference superseded by DW/144 (2013, updated 2016).

Insulation: condensation governs in Doha

ASHRAE 90.1 sets insulation R-values for energy. In Doha the design dew point of about 30 °C (0.4 % annual) means any duct or pipe surface below 30 °C exposed to outdoor or unconditioned air sweats, and roof voids and plant rooms are often at outdoor humidity. The insulation thickness is therefore set by the condition that the outer surface of the insulation stays above the dew point of the surrounding air, with an unbroken vapour barrier on the warm side, and then checked against the energy minimum. Typical Gulf practice: 25 mm glass fibre with foil facing inside conditioned ceiling voids, 50 mm with vapour barrier and aluminium cladding on roofs and in plant rooms, and closed-cell elastomeric on refrigerant and condensate pipes. QCS 2014 Section 22 Part 7 carries the thickness tables (to be confirmed clause by clause); Dubai's 502.11 tables are the published regional reference.

Acoustic lining deserves a caution. Fibrous lining inside ducts carrying humid air is a hygiene and durability risk; ASHRAE 62.1 §5.4 requires liners resistant to erosion and moisture. Prefer external insulation with duct attenuators, or coated/closed-cell liners where lining is unavoidable, and never line ducts downstream of a cooling coil before the air is dry.

Dampers and the drawings that carry them

  • Volume control dampers at every branch (the design basis says so), positioned where they can be reached and where their noise does not reach the room (not at the diffuser neck for NR 30 rooms).
  • Fire dampers (UL 555 or BS EN 1366-2 / BS EN 15650) wherever ductwork crosses a fire-rated wall or floor, at shaft entries and exits; fusible link 72 °C standard; access door within reach on the drawing, not only in the specification.
  • Smoke dampers and combination dampers (UL 555S) where smoke control or HVAC shutdown zoning requires it; motorised, with FACP interlock and BMS status.
  • Gas-tight dampers on all intakes and exhausts, normally closed on fire-and-gas emergency, per the client's fire and safety philosophy (a process-plant requirement carried into this project; confirm its applicability rather than delete it).
  • Backdraft dampers on exhaust discharges; sand-trap louvres on intakes at 1 m/s; exhaust louvres at 2–2.5 m/s on gross area.

Read

  • A
    Duct sizing chart (KAIA project) — an ASHRAE friction chart for round duct (ρ = 1.20 kg/m³, ε = 0.09 mm) with a design friction line at 1.25 Pa/m and hand-written rectangular equivalents. Use it to practise reading diameter and velocity for an airflow at a friction rate, then compare with this project's 0.4–0.8 Pa/m.
  • B
    Recommended Noise Criterion sheet — NR targets by room and the attenuator length versus insertion loss table; the crosstalk rule (attenuator velocity ≤ 1.5 m/s, ≤ 10 Pa).
  • C
    HVAC Design Guidelines (corporate extract) §10.3 — G90 galvanised duct, seal all transverse and longitudinal seams regardless of pressure class, pressure-test before insulating, duct insulation R-10 (about 1.76 m²K/W) minimum: a stricter owner's rule than most codes and a useful benchmark.
  • D
    Dubai Green Building Regulations 502.11 (pipe and duct insulation to prevent condensation, BS 5422 inside, tables outside) and 502.13 (leak-test all ductwork above 250 Pa and all ductwork outdoors or in unconditioned space).
  • E
    ASHRAE Design Manual — louvre and damper face velocities, sound-trap limit of 10 m/s, and the supply-air yardstick of 3–4 L/s·m² for offices.

Qatar rules that touch this module

  • Partial
    QCS 2014 Section 22 Part 6 Ductwork and Air-Side Equipment; Part 7 Thermal Insulation; Part 9 Accessories — galvanised sheet grade, fabrication per ASHRAE/SMACNA or DW/144, insulation thickness and vapour barrier tables, silencers and vibration isolation. Clause-level content to be confirmed from the PDF.
  • Partial
    QCDD 2022 Technical Requirements Guide and 2015 annex ACMV_N1 — fire and smoke dampers at rated separations, duct penetrations, HVAC shutdown on alarm, smoke-control duct temperature ratings (car-park extract fans rated 300 °C for 2 h in the QCDD car-park annex). NFPA 90A applies where the guide is silent.
  • Verified
    NFPA 90A-2024 — installation of air-conditioning and ventilating systems: duct materials, fire and smoke damper locations, smoke detectors in return air and shutdown; the standard the design basis invokes for emergency ventilation.
  • Verified
    DW/144 (BESA) and SMACNA HVAC Duct Construction Standards — the two construction standards; the specification must choose.
  • Verified
    ASHRAE 62.1 §5.4 / §5.5 — duct liners resistant to moisture and erosion; drain pans and coil access; relevant to the design basis's acoustic-lining requirement.

Duct sizer (equal friction)

Round diameter from Darcy–Weisbach with the Altshul–Tsal friction factor (ρ = 1.2 kg/m³, ε = 0.09 mm galvanised), then the Huebscher rectangular equivalent for a chosen height. Checks against design basis Table 4-7.

Round diameter mm
Velocity (round) m/s
Rectangular (W × H) mm
Velocity (rectangular) m/s

Worked example: a fan-coil supply main and its static pressure

1
Ducted FCU serving a clubhouse lounge, 1,000 L/s. At the design basis's 0.4 Pa/m the round size is 530 mm at 4.5 m/s, exactly at the Table 4-7 ceiling. With a 300 mm ceiling-void constraint the Huebscher equivalent is about 850 × 300 (aspect ratio 2.8:1), which runs at 3.9 m/s.
2
Acoustics: lounge NR 40 above a suspended ceiling allows about 8.9 m/s in the main; 3.9 m/s is comfortable. If the same duct served a bedroom at NR 30 within the occupied space, the ceiling would be about 6 m/s (interpolating RC 25–35): still fine, but the diffuser at 2.0 m/s would be the constraint.
3
External static: 28 m of main at 0.4 = 11 Pa; fittings (two elbows, four branches, one transition) ≈ 35 Pa; volume dampers 10 Pa; diffusers 20 Pa; return grille and 8 m of return duct 25 Pa; dirty MERV 8 filter allowance 60 Pa. Total ≈ 160 Pa.
4
The schedule shows a low-static FCU family (50 Pa ESP). The unit cannot deliver 1,000 L/s against 160 Pa; either a medium/high-static ducted unit or a shorter, larger duct is required. This is the comment, not "duct undersized".
Sizing the duct and selecting the fan are one calculation. A schedule that lists airflow without external static, or a duct drawing without a pressure-drop summary, cannot be reviewed for either.

Review checklist: duct drawings, sizing tables and the duct specification

Self-check

  1. 2,500 L/s of fresh air at the design basis's 0.8 Pa/m: what round size and velocity, and is it within Table 4-7?

  2. Why must the filter pressure drop in the ESP be the dirty value?

  3. A specification says "ductwork to DW/144 Class A leakage, pressure class high". What is inconsistent?

  4. Insulated supply duct in a roof void at 42 °C and 24 g/kg: what surface temperature must the insulation's outer face keep, and which property of the insulation must be unbroken?

  5. Where do the design basis's gas-tight dampers come from, and what do you do about them in an accommodation project?

  6. What is a crosstalk attenuator and when does the NR sheet require one?

Flashcards

Next: Module 7, refrigerant and condensate piping.

Week 2 · Module 7 · about 2.5 hours

Refrigerant and condensate piping

Two pipe systems carry the consequences of every earlier decision: the refrigerant lines that must return oil and deliver liquid without flashing across a hot roof, and the condensate lines that carry away the litres per hour a humid climate produces. Both are routinely under-drawn. This module gives you the sizing physics, the manufacturer-rule boundary for VRF, and the condensate arithmetic.

Why it matters

Refrigerant piping problems arrive months after handover as compressor failures (oil starvation), capacity complaints on the far rooms (pressure drop and flash gas) and wet ceilings (condensation on uninsulated suction lines). Condensate problems arrive in the first humid week as dripping diffusers and stained ceilings. Both are cheap to prevent on drawings and expensive to fix behind finishes.

Concept

Three lines and what each must do

  • Suction (low-pressure gas): carries cold vapour and entrained oil back to the compressor. It must be sized for a pressure drop small enough not to lose capacity (a drop equivalent to about 0.5–1 K of saturation temperature; 2 °F loses roughly 4 % capacity) and a velocity high enough to carry oil up risers. It is always insulated.
  • Liquid line: carries subcooled liquid to the expansion device. Its enemy is flash gas: pressure lost to friction and to static lift (a rising liquid line loses about 10 kPa per metre for R-410A) plus heat gained on a sunny roof can bring the liquid to saturation before the valve, and the expansion valve then hunts. The remedy is subcooling margin and insulation on exposed runs. Velocity is kept below about 1.5 m/s to avoid liquid hammer when solenoids close.
  • Discharge / hot gas: hot vapour from compressor to condenser (split systems) or the high-pressure gas line of a heat-recovery VRF. Sized like suction but at higher density; insulated for personnel protection above about 66 °C.

Oil return numbers, and why two references disagree

Your library gives two minimum velocities for oil return: McQuay AG 31-011 says 2.5 m/s (500 fpm) horizontal and 5 m/s (1,000 fpm) in risers; the DuPont/Suva handbook says 3.8 m/s (750 fpm) and 7.6 m/s (1,500 fpm). Both are legitimate rules from different eras and oils. A calculation must state which basis it uses; the stricter one is safer for part-load operation, which is where risers fail. Where a compressor unloads to 25–50 %, a double riser keeps velocity up: the small riser carries the minimum load, the large one is sealed by an oil trap at low load and opens at full load. Lines slope toward the compressor (about 1:100 to 1:200), and risers get a trap at the base per the manufacturer's rule.

VRF: the manufacturer's rules replace the generic ones

For VRF the pipe sizes are tabulated by the manufacturer against the downstream capacity index, the branch joints (refnets or headers) are proprietary, and the additional refrigerant charge is a per-metre figure by liquid-line diameter. The generic physics still applies, but the review question changes: show the manufacturer's selection printout for every circuit, with pipe sizes, joint types, lengths, level differences, additional charge and the capacity correction. Installation rules are equally specific: brazing under nitrogen purge, pressure test at the R-410A design pressure (4.15 MPa) for 24 hours, triple evacuation to below 500 microns (−100.7 kPa), and charge by weight. These belong in the method statement and the inspection and test plan, and they are the items that determine whether the warranty is valid.

Insulation on refrigerant lines in Doha

A suction line at 8–12 °C in 30 °C dew-point air sweats through any gap. Closed-cell elastomeric insulation (ASTM C534 / BS 5422 thickness tables), 13–19 mm inside conditioned ceiling voids and 25 mm outdoors, on both lines (the liquid line for solar gain, the gas line for condensation), with UV-stable cladding or jacket on the roof, and sealed joints. Where two insulated lines share a trunking, the trunking must drain. The design basis's condensate-pipe cladding requirement (aluminium sheet outdoors) is the same logic.

Condensate: how much, how big, how steep, where to

Condensate mass equals the latent load divided by the latent heat of vaporisation (about 2,450 kJ/kg): 10 kW of latent cooling produces 14.7 kg/h, i.e. about 15 L/h. At Gulf design conditions a fresh-air unit is 60–80 % latent, so a 150 kW TFAHU makes around 150 L/h at peak, a bath every eight minutes. Sizing then follows a capacity table (the International Mechanical Code table is the common reference: up to 20 tons ¾ in., 21–40 tons 1 in., 41–90 tons 1¼ in., 91–125 tons 1½ in., 126–250 tons 2 in.; verify against the current IMC edition before citing) with a minimum slope of 1 % (1:100) toward the drain, cleanouts at changes of direction, and no reduction in size along the run. A draw-through unit needs a trap whose depth exceeds the negative static at the coil (trap depth ≥ 1.5 × static, plus 25 mm), or the drain pan will not drain while the fan runs; a blow-through unit needs a trap to stop air blowing out. Ceiling-mounted units get a secondary drain pan or a float switch that stops the unit. Condensate pipe is itself cold (12–15 °C) and sweats: insulate it in ceiling voids and clad it outdoors, as the design basis requires. Discharge: the design basis sends condensate to the storm-water network with an air break; a project pursuing GSAS water credits can recover it for irrigation instead.

Chilled water, for completeness

Not used on this project, but you will see it elsewhere: closed-loop chilled-water pipe is sized to about 150–300 Pa/m friction with velocities from 0.9 m/s (small bore, to avoid air-locking and noise) to about 2.5–3 m/s in large mains, per ASHRAE Fundamentals Chapter 22 (older editions Chapter 35). The verification sheet in your library from another project draws exactly that: a 150 Pa/m line up to 300 mm and a velocity-limited line above.

Read

  • A
    McQuay AG 31-011 Refrigerant Piping Design Guide — the most usable document in the library on this topic: 500 / 1,000 fpm oil-return rule, 1/8 in. per ft slope, double-riser logic, the 4 °F additional subcooling at the expansion valve, insulation of liquid lines routed at roof level, SI capacity and velocity tables for R-410A in Appendix 3. Excludes VRF explicitly.
  • B
    DuPont Suva Refrigerant Piping Handbook — the 1 °F-per-line design goal, 750 / 1,500 fpm minimums, capacity loss per °F of line loss (2 °F suction ≈ 4.3 %), double-riser pairing table, equivalent lengths of fittings, hanger spacing. Imperial, older refrigerants; read for the physics.
  • C
    Condensate Pipe Sizing note — states the principle (sizes selected by coil cooling duty); its table is an embedded image, so read it in Word and compare with the IMC table above.
  • D
    Chilled water pipework sizing verification — the friction-chart method (2001 ASHRAE Fundamentals Chapter 35) applied at 150 Pa/m with a velocity limit above 300 mm; a model for how a sizing verification should be presented.

Qatar rules that touch this module

  • Partial
    QCS 2014 Section 22 Part 2 and Part 3 — refrigerant pipework materials, brazing, testing and charging for central and unitary equipment; Part 7 insulation. Clause text to be confirmed.
  • Partial
    QCS 2014 Section 19 Plumbing Work; Section 20 Drainage; Ashghal QSDDM 2005 — condensate discharge to drainage and the storm-water network; the design basis's plumbing section routes condensate to storm.
  • Verified
    ASHRAE 15-2022 / ISO 5149 / EN 378 — refrigerant piping through occupied spaces, concentration limits (Module 4), pressure relief and machinery-room criteria; ASTM B280 / EN 12735 copper tube for refrigeration.
  • Verified
    International Mechanical Code §307 (condensate disposal, drain sizing table, traps, secondary drains) — widely adopted in Gulf specifications; the design basis's plumbing tables cite IPC 2021, so IMC 2021 is the consistent companion.
  • Verified
    BS 5422 / ASTM C534 — insulation thickness for below-ambient pipework; Dubai GBR 502.11 as the published regional table.

Worked example: condensate from a treated-fresh-air unit

1
TFAHU 2,136 L/s (Module 3) at 34 °C / 32 °C WB to 12 °C saturated off-coil before the heat pipe reheat. Moisture removed = 2.136 m³/s × 1.2 kg/m³ × (0.0298 − 0.0087) kg/kg = 0.054 kg/s = 195 kg/h, about 3.2 L/min.
2
Cross-check by latent load: 0.054 kg/s × 2,450 kJ/kg = 132 kW latent of the 184 kW coil (SHR 0.28), consistent with Module 1.
3
Pipe: the unit is about 52 TR, so the IMC table gives 1¼ in. (32 mm) minimum; at 1 % slope a 32 mm uPVC pipe carries well over 3 L/min. Use 40 mm if the run collects other units.
4
Trap: draw-through unit with −450 Pa at the coil section → trap depth ≥ 1.5 × 45 mm + 25 mm ≈ 95 mm water seal; pan height above the drain must accommodate it, which is a unit-selection detail often missed.
5
Route: insulated in the plant room (the pipe runs at about 12 °C in 30 °C dew-point air), aluminium-clad outdoors, cleanout at each direction change, air break before the storm drain, and no connection to a foul drain without a trap and vent.
One fresh-air unit produces about 200 L/h at design. Multiply by the number of units on a roof before accepting a single 25 mm header, and check the roof drain it discharges to is on the storm system the wet-utilities design expects.

Review checklist: refrigerant and condensate piping drawings and calculations

Self-check

  1. A split-system suction riser is 9 m tall and the compressor unloads to 50 %. What do you look for on the isometric?

  2. Why insulate the liquid line on a roof if it is warm anyway?

  3. How much condensate does a 28 kW VRF outdoor unit's indoor units produce at design if the SHR is 0.75?

  4. What is wrong with a condensate drain that discharges into a floor drain of the foul system?

  5. What evacuation and test values would you expect in a VRF method statement?

  6. Chilled water is not on this project. What two limits would you still recognise on a chilled-water sizing sheet?

Flashcards

End of Week 2. Next: Module 8, special rooms.

Week 3 · Module 8 · about 2.5 hours

Special rooms: substations, batteries, pumps, generators, kitchens, laundry, clinic

Rooms whose HVAC exists to protect equipment or remove a hazard follow different rules from rooms for people: the load is electrical loss, the ventilation is dilution or purge, the pressure is a barrier, and failure has consequences beyond comfort. This module walks each room type through the numbers the design basis fixes and the ones it leaves to you.

Why it matters

A substation designed to a "10 ACH" line without asking what the air is will get a fan that could cool nothing or a coil that could cool a hall. A battery room ventilated to the letter of a European dilution formula will breach the client's prescriptive rule by a factor of a hundred. A kitchen hood without its make-up air pulls the dining hall negative and the outdoor air in through the doors. These rooms are where the reviewer earns trust with the electrical, fire and catering disciplines, because their requirements land on the HVAC drawings.

Concept, room by room

Substations and electrical rooms: cooling first, pressure second, purge last

The load is equipment loss: transformer no-load and load losses (roughly 1 % of rating for dry-type units at full load), switchgear and busbar losses, UPS rectifier and inverter losses, cable losses, plus lights and solar gains through a usually windowless envelope. A design basis figure such as 50 W/m² is a placeholder until the electrical schedule exists; two 1,600 kVA dry-type transformers alone reject about 30 kW, which in a 242 m² room is 125 W/m². Get the loss schedule from electrical before accepting any substation load.

Temperature: switchgear is rated to 40 °C ambient by IEC 62271 and transformers by their insulation class, so 23 °C is a client comfort-and-longevity choice, not a code requirement; it costs capacity because the coil runs closer to the space temperature. Redundancy: an accommodation project substation that trips on HVAC failure in August loses the project, so N+1 packaged units or a ventilation fallback mode with temperature alarms to the BMS are ordinary practice even where the design basis is silent, as this one is.

Now the three quantities that get confused. Supply air at about 8–12 ACH of recirculated, cooled air is normal for a DX-cooled electrical room: 10 ACH of a 968 m³ room is 2,690 L/s, which removes 12 kW at a 3.7 K supply-to-room difference, or 30 kW at 9 K. Pressurisation air is filtered outdoor air sized by leakage to hold the overpressure: at +50 Pa through a reasonably tight room perhaps 0.5–1 ACH (135–270 L/s), which at 47 °C / 30 °C WB costs 9–18 kW of cooling, comparable with the entire internal load, and needs an airlock. Emergency ventilation (purge on smoke or on cooling failure) is a separate mode with its own fan and dampers, and its ACH is not the normal-mode figure. A design that writes "10 ACH" must say which of the three it means; a design that gives all three is reviewable.

Battery rooms: dilution formula, prescriptive rule, and the interlock

Lead-acid batteries evolve hydrogen on charge. EN 50272-2 (now IEC 62485-2) sizes dilution ventilation as Q = 0.05 × n × Igas m³/h, where n is the number of cells and Igas the gas-producing current (about 1 A per 100 Ah in float for vented cells), reduced by factors f1 = 0.5 for low-antimony cells and f2 = 0.5 for valve-regulated cells; natural ventilation openings then need A ≥ 28 × Q cm². A 110-cell, 400 Ah VRLA bank in float needs about 5.5 m³/h. A prescriptive 12 ACH rule for a 60 m³ room gives 720 m³/h, over a hundred times more; the prescriptive rule governs because it is the client's, and its purpose is safety margin for boost charging and failures. What the formula adds is the logic: extract at high level (hydrogen is light), inlet at low level, at least 2 m between them, no recirculation, fan run-on for an hour after boost charge, and the charger interlock the design basis requires so that a failed extract stops the charging that makes the gas. A hydrogen detector with alarm at 1 % (25 % of the lower explosive limit) is the modern complement. The design basis asks for explosion-proof duty/standby fans; the European standard argues a diluted room need not be Ex-rated, but a Level-1 client requirement overrides that argument. Batteries also want 20–25 °C for life (VRLA life halves for every 10 K above 25 °C), which is a cooling requirement the design basis does not list for battery rooms; ask for it.

Pump rooms and fire pump rooms

Domestic water and fire pump rooms are motor-heat rooms held at 24 °C by fan-coil units in normal mode. A diesel fire pump adds combustion and radiator air when running, per NFPA 20 and the engine manufacturer, and the design basis specifies 10 ACH in emergency mode with supply and exhaust fans interlocked, fed by two-hour fire-rated cables and started by the fire alarm panel. The review point is the louvre and duct sizing for the engine's radiator discharge and combustion air at 47 °C ambient (derate the engine), and the switching logic between fan-coil normal mode and purge mode so that the two do not fight.

Generator rooms and fuel rooms

NFPA 37 governs. The design basis defines three states: 6 ACH with the set off, 10 ACH on standby, and radiator discharge plus combustion make-up air when running, with fuel-tank rooms at 10 ACH continuously. The running case sizes the intake louvre (engine data, at 2–2.5 m/s free-area velocity), the discharge duct or hood, and the attenuators that keep the set within the site noise limit; the standby case keeps the room below the alternator's ambient limit while the set idles; the off case is the summer heat soak. Day tanks inside the room (8 hours in this design) bring fuel vapour rules: diesel's flash point above 55 °C keeps the room unclassified, but leak detection, bunding and a fusible-link fuel shut-off at 75 °C are in the fuel-oil section of the design basis and must appear on the HVAC cause-and-effect matrix.

Fire command centre

Positively ventilated in supply mode at 12 ACH during emergency per QCDD, with its own air conditioning, separated by two-hour construction, started by the fire alarm panel and the sprinkler flow switch, on two-hour cables. Positive pressure keeps smoke out of the one room that must stay occupied.

Commercial kitchens

NFPA 96 and ASHRAE Applications Chapter 34 rule the hood. Exhaust is set by hood type and appliance duty (light, medium, heavy, extra-heavy), broadly 300–600 L/s per metre of wall-canopy hood; make-up air at 80–90 % of exhaust, delivered cooled through a make-up air unit so the kitchen stays slightly negative to the dining room and the dining room stays positive to outside. Grease ducts are welded steel, sloped back to the hood, with cleanouts, enclosed or wrapped for two hours, discharging away from intakes; the fan motor sits outside the airstream. Ecology units clean the discharge in stages (pre-filter, bag filter, electrostatic precipitator, activated carbon) and add pressure drop that the exhaust fan must overcome at dirty condition. The wet-chemical suppression system interlocks with the hood: on discharge, make-up air stops, exhaust continues, and the LPG solenoid closes; the interlock belongs on the HVAC cause-and-effect matrix as much as on the fire one. Kitchen appliance heat gains were deferred in the design basis; the hood removes a large share of them, which is why the load calculation and the hood calculation must be done together.

Central laundry

Tumble dryers exhaust hot, wet, lint-laden air, typically 300–600 L/s each per manufacturer, through lint interceptors into a dedicated extract with anti-static impellers and the motor outside the airstream (the bifurcated fan in the design basis); make-up air must replace it or the laundry runs negative and hot. The design basis names the equipment but gives no temperature, humidity, airflow or lint-load target for the laundry, and assigns its extract rate to the "kitchen specialist"; ask for the laundry equipment schedule, the exhaust per machine, the room design condition and the make-up air, and expect an internal load dominated by equipment (drying, ironing, washing) rather than people.

Clinic

ASHRAE 170 sets total and outdoor air changes and pressure relationships per room type: examination and treatment rooms 6 total / 2 outdoor ACH, waiting areas 12 / 2 and negative to adjacent, toilets 10 exhaust, clean storage positive. "2 ACH" without "outdoor" is incomplete; the schematic submission must tabulate both numbers and the pressure sign per room.

Hazardous areas: context you will meet elsewhere in the site

Not this project's problem, but the origin of several of its design-basis rows. In classified areas (IEC 60079-10-1 zones; the client uses the zone system, API RP 505, not the division system of API RP 500) a building is protected by pressurisation: IEC 60079-13 requires at least 25 Pa overpressure against the adjacent zone, purge before energising, and loss-of-pressure actions; NFPA 496 does the same with Type X/Y/Z purging. Intakes are placed outside the classified zone and above the height where hydrocarbons may collect, with gas detection that closes the gas-tight dampers and shuts the HVAC. That is the logic behind the design basis's normally-closed intake dampers and its 10 m separation and "above the risk zone" intake rules.

Read

  • A
    EXIDE battery room ventilation and installation (prEN 50272-2) — the Q = 0.05·n·I formula, f1/f2 factors, A ≥ 28Q cm² openings, 2 m inlet-outlet separation, 0.5 m spark clearance, +5 to +25 °C room temperature, one-hour run-on. Written to a 2000 draft; the published EN 50272-2:2001 and IEC 62485-2 changed some values.
  • B
    ASHRAE 62.1-2013 Table 6.5 — exhaust rates for auto repair, chemical storage, refrigerating machinery rooms, janitor and laundry spaces, and the air-class rules that forbid recirculating Class 3 and 4 air.
  • C
    CIBSE TM37 Appendix A — equipment gains for industrial process areas (50 W/m²), workshops and warehouses; a sanity check for workshop and laundry internal loads.
  • D
    HVAC Design Guidelines (corporate extract) — server rooms on independent systems with loads from equipment manufacturers; laboratories at 8–10 ACH; the principle that special rooms get their own plant.

Qatar rules that touch this module

  • Partial
    QCDD 2015 annexes FLS_A7 Electrical Room, FLS_A8 Substations, FLS_A5 Fire Command Centre, FLS_A6 Fire Pumps and Pump Room; 2022 Technical Requirements Guide — separation, access, ventilation and emergency-power requirements for these rooms; FCC minimum 6 m² with 2-hour separation in the older QCDD fire-safety standard.
  • Verified
    NFPA 37 (stationary engines), NFPA 20 (fire pumps), NFPA 110 (emergency power), NFPA 96 (kitchen exhaust) — the standards the design basis invokes for generator, fire-pump and kitchen ventilation; editions to match the design basis's fire-fighting code table (NFPA 20-2022, 110-2022).
  • Verified
    IEC 62485-2 (ex EN 50272-2) and IEEE 484 / IFC §1207 (hydrogen ≤ 1 %, or 5.1 L/s·m² mechanical ventilation) — the two families of battery-room rules; the design basis's 12 ACH exceeds both.
  • Verified
    ASHRAE 170-2021 — ventilation of health-care facilities; total and outdoor ACH and pressure relationships by room type for the clinic.
  • Verified
    IEC 60079-13, NFPA 496, API RP 505, ISO 15138 — pressurised and ventilated rooms in classified areas; the client context; the source of the +50 Pa rows.
  • Unverified
    the client the client's minimum design requirements for building services; the client's workers-accommodation regulation — expected to carry the client's substation, battery-room and pressurisation rules; obtain and cite clause numbers before challenging Table 4-5.

Battery-room ventilation: dilution formula versus prescriptive ACH

Q = 0.05 × n × I × f1 × f2 (m³/h) with I = Igas × Ah / 100; natural-ventilation opening A ≥ 28 × Q cm². Compare with the design basis's 12 ACH.

Dilution Q m³/h
Natural opening A cm²
Prescriptive flow m³/h
Ratio prescriptive / dilution

Worked example: decomposing "substation 10 ACH, +50 Pa, 23 °C"

1
Room 242 m² × 4 m = 968 m³. Electrical loss schedule (to be obtained): assume 2 × 1,600 kVA dry-type transformers at 0.9 % losses (29 kW) + switchgear 4 kW + lights 16 W/m² (4 kW) + envelope 5 kW = 42 kW, i.e. 174 W/m², against the placeholder 50 W/m² (12 kW).
2
Supply air for 42 kW at a 10 K coil difference: 42 / (1.2 × 10) = 3.5 m³/s = 13 ACH. The "10 ACH" is therefore a recirculated supply figure of the right order; write it as such on the schedule.
3
Pressurisation: leakage at +50 Pa through doors and penetrations, say 200 L/s of filtered outdoor air (crack calculation to be shown). Cooling cost at 47 °C / 30 °C WB to 23 °C / 50 %: about 6.7 kW per 100 L/s → 13 kW, a third of the internal load, plus an airlock. If the client confirms the "general building +1 ACH" row applies instead, the make-up is 270 L/s but at a few pascals and without the airlock.
4
Purge mode: on smoke detection or on both packaged units failing, a separate exhaust and intake path at, say, 10 ACH (2,690 L/s) with dampers, on emergency power, and high-temperature alarm at 35 °C to the BMS.
5
Plant: 2 × 100 % (N+1) packaged units at 47 °C-derated capacity ≥ 55 kW each, sand-trap louvre at 1 m/s (0.2 m² for 200 L/s), coated coils, and the 65 dB(A) at 1 m noise check.
"10 ACH, +50 Pa, 23 °C" unpacks into 13 ACH of cooled supply, 200 L/s of pressurisation air costing 13 kW, a separate purge mode, and an N+1 plant decision the design basis never made. Each line is a review comment with a number attached.

Review checklist: special rooms

Self-check

  1. A battery room drawing shows extract at low level "because acid fumes are heavy". What do you write?

  2. Why is the pressurisation air for a +50 Pa substation more expensive than its supply air?

  3. The generator room ventilation calculation uses the engine's radiator airflow at 25 °C ambient. What is missing?

  4. Kitchen hood exhaust 3,500 L/s, make-up air 3,500 L/s. Is the balance right?

  5. Which two numbers does ASHRAE 170 require for an examination room, and what did the design basis give?

  6. State the IEC 60079-13 minimum overpressure and explain in one sentence why it is not a target for a project substation.

Flashcards

Next: Module 9, fire and life-safety interfaces.

Week 3 · Module 9 · about 1.5 hours

Fire and life-safety interfaces and smoke management

HVAC is the system that moves smoke, so the fire strategy tells it when to stop, when to run, and what to close. This module maps the Qatar approval path, the NFPA documents Civil Defence leans on, and the cause-and-effect matrix that ties the fire alarm panel to every damper and fan on your drawings.

Why it matters

Qatar Civil Defence approves the mechanical ventilation and smoke-control package separately (DC2) after the architectural life-safety approval (DC1), on drawings stamped by a QCDD-approved mechanical engineer. A missing fire damper, an air-handler without a duct smoke detector, or a substation purge fan on non-rated cable is a rejection that arrives when the ceilings are closed. On a operator-controlled site the client's own fire-and-gas philosophy adds requirements the municipal path never asks for, such as gas-tight normally-closed intake dampers.

Concept

Who approves what

StageAuthorityPackageWhat the mechanical reviewer must have ready
Building permit (e-BP)Ministry of MunicipalityArchitectural and services drawings; service-authority approvalsKahramaa cooling-load summary and equipment schedule; insulation approval
DC1QCDDLife-safety and fire-strategy drawingsFire zoning, egress, smoke-control concept the HVAC will implement
DC2QCDDFire alarm, firefighting, mechanical ventilation and smoke controlVentilation and smoke-control drawings, damper schedules, cause-and-effect matrix, fan ratings, emergency power; stamped by a QCDD-approved mechanical engineer
Client reviewthe client (and Industrial Cities DPE at RLC)All deliverables against the corporate philosophy and the FEEDCompliance with the client's fire and safety philosophy, the fire life safety strategy and the FEED design basis
CompletionQCDD, Kahramaa, clientCompletion certificate; periodic testingCommissioning records for smoke control, damper tests, HVAC shutdown test

The documents behind the approvals

QCDD's governing text is the Civil Defence Technical Requirements Guide 2022 (with a 2023 update), which supersedes the 2015 Fire Safety Guidelines but sits on top of the 2015 annexes: FLS_A1 refuge floors, A2 smoke-stop and firefighting lobbies, A3 external access, A4 fire lifts, A5 fire command centre, A6 fire pumps, A7 electrical rooms, A8 substations, FFS and FAS notes, and ACMV_N1, the air-conditioning and mechanical ventilation notes. Where the guide is silent it adopts NFPA as the principal reference: NFPA 101 (means of egress), 5000 (building construction), 90A (installation of air-conditioning and ventilating systems), 92 (smoke control), 96 (kitchen exhaust), 72 (alarm), 13 (sprinklers), 20 (fire pumps), 37 and 110 (engines and standby power). QCDD does not publish which NFPA edition it enforces; the safe assumption is the current one, and the design basis's fire-fighting code table pins 2022–2024 editions for the client review.

NFPA 90A: the four HVAC rules that recur

  • Duct smoke detectors: in the supply downstream of filters for systems above 944 L/s (2,000 cfm), and in the return at each floor or where the return exceeds 7,080 L/s (15,000 cfm) serving more than one floor; detection stops the fan and closes smoke dampers via the fire alarm panel. The design basis puts detectors in AHU return ducts and shuts the unit through the fire annunciation panel.
  • Fire dampers at rated walls, floors and shaft penetrations; smoke dampers where ducts cross smoke barriers or where the smoke-control concept requires; combination dampers where both apply (Module 6 carries the drawing checklist).
  • Duct materials and clearances: non-combustible ducts, flexible duct limits, clearances from combustibles, plenum rules for return-air ceilings (no combustible cabling or insulation without a plenum rating).
  • System shutdown on alarm as the default; systems that must run in a fire (smoke control, pressurisation, fire pump and command-centre ventilation) are the exceptions and get rated cable and emergency power.

Smoke control: what a G+2 project needs and what it does not

Stair pressurisation (NFPA 92: 12.4 Pa minimum across a closed stair door in sprinklered buildings, 24.9 Pa unsprinklered, door force at most 133 N; BS EN 12101-6 class systems at 50 Pa) is a high-rise and enclosed-stair measure that the QCDD fire strategy decides at DC1; low-rise accommodation with open or naturally ventilated stairs may not need it. Mechanical smoke extract applies to large undivided spaces (mess halls, mosques, warehouses) where the strategy calls for it, to enclosed car parks (QCDD: 6 ACH normal, 10 ACH smoke mode, fans rated 300 °C for 2 hours) and to basements. The design basis lists smoke management per the client's fire life safety strategy, names UL-listed equipment, and treats post-fire purge as a non-life-safety convenience. The reviewer's task is to obtain the strategy, list every space where it demands a smoke-control function, and see that the HVAC drawings implement exactly that list, no more and no less.

Fire and gas on a operator-controlled site

a Qatar industrial city buildings follow the client's corporate philosophy for fire and safety: hydrocarbon or H2S detection at air intakes trips the HVAC and closes gas-tight, normally-closed dampers on intakes and exhausts, so an external release cannot be drawn into an occupied building; intakes sit high and upwind. The project design basis carries these rules over. Deleting them is a client decision; implementing them means a detector at each intake, damper actuators with position feedback, and the shutdown logic on the matrix.

The cause-and-effect matrix

One table, rows are initiating events (smoke detector zone, duct detector, sprinkler flow switch, manual call point, gas detector, kitchen suppression discharge, fan failure, high room temperature), columns are actions (stop AHU, close smoke damper, start purge fan, open relief damper, close LPG solenoid, start FCC ventilation, signal BMS). It is the single document that lets the fire, electrical, controls and mechanical reviewers check each other; ask for it with the first schematic and refuse to sign off ventilation drawings without it.

Read

  • A
    HVAC Design Guidelines (corporate extract) — FM Global and NFPA references in an owner's guideline; the reminder that an owner's fire insurer may add requirements beyond the authority's.
  • B
    Dubai Green Building Regulations 401.09 — car-park ventilation (CO < 50 ppm, 6 ACH or CO-controlled, 10 ACH smoke clearance): the regional analogue of the QCDD car-park annex, useful if the project adds enclosed parking.

Qatar rules that touch this module

  • Verified
    Law 13/1997 on Civil Defence as amended by Law 9/2012 — legal basis for QCDD drawing review, completion inspection and certificates. (Vendor blogs citing "Law 9/1993" are wrong.)
  • Partial
    Civil Defence Technical Requirements Guide 2022 (2023 update) and the 2015 annexes incl. ACMV_N1 — smoke control, pressurisation, dampers, ventilation of special rooms, kitchen exhaust; NFPA as principal reference; chapter numbers and numeric criteria to be confirmed from the MoI PDF.
  • Partial
    QCDD approval process DC1 / DC2 — mechanical ventilation and smoke control reviewed at DC2 after DC1; drawings by a QCDD-approved mechanical engineer; MEP submissions only after DC1 approval.
  • Verified
    NFPA 90A-2024, NFPA 92-2024, NFPA 96, NFPA 101-2024 — current editions; the design basis's fire code table pins 101-2024 and 5000-2024.
  • Partial
    QCDD car-park annex (QCD FSS 7.2) — 6 ACH normal with CO ≤ 25 ppm, 10 ACH smoke mode, design fires 4 MW sprinklered / 8 MW, fans 300 °C for 2 h, emergency power.
  • Unverified
    the client's fire and safety philosophy Corporate Philosophy for Fire and Safety; the client Fire Life Safety Strategy for the project — not public; obtain from the client's document control before finalising the cause-and-effect matrix.

Worked example: a cause-and-effect row for the mess hall

Initiating eventStop dining AHU / VRF IDUsClose smoke dampersKitchen exhaust (ecology)Kitchen MAHULPG solenoidIntake gas-tight dampersFCC ventilationBMS
Dining smoke detector zoneStopCloseRunStopStartAlarm
AHU return duct detectorStop that AHUClose that zoneAlarm
Kitchen wet-chemical dischargeRunStopCloseAlarm
Gas detector at roof intake (client philosophy)Stop allStopStopCloseClose (NC)StartAlarm
Sprinkler flow switchStopCloseStartAlarm
Post-fire purge (manual, fire officer)OpenLog
Illustrative only. The client's fire life safety strategy and the fire alarm designer own the final matrix; the HVAC reviewer checks that every device on the mechanical drawings appears in a column and every column has a wired path.

Review checklist: fire and life-safety interfaces on HVAC deliverables

Self-check

  1. At which QCDD stage are mechanical ventilation drawings reviewed, and what must precede it?

  2. An 850 L/s ducted VRF indoor unit serves a clubhouse lounge. Does NFPA 90A require a supply duct smoke detector?

  3. Why is post-fire smoke purge treated differently from smoke control?

  4. What does a gas detector at an intake do on a operator-controlled site, and what proves it on the drawings?

  5. Which two Qatar laws underpin QCDD's authority?

  6. Name three exceptions to "HVAC stops on alarm".

Flashcards

Next: Module 10, controls, BMS and energy compliance.

Week 3 · Module 10 · about 1.5 hours

Controls, building management and energy compliance

Controls decide whether a correctly sized system behaves; energy rules decide whether the authority lets it be built. This module covers the control architecture the design basis prescribes, the sequences worth reading line by line, and the two compliance regimes, Kahramaa and GSAS, whose submittals are built from the same numbers you reviewed in Modules 2 and 5.

Why it matters

A treated-fresh-air unit with a perfect coil and no dew-point control delivers 60 % RH air on a humid morning. A substation with two packaged units and no changeover logic runs one to death. A cooling-load summary that disagrees with the equipment schedule fails the Kahramaa check and stalls the permit. Controls and compliance are where a reviewer's earlier findings either become wiring and paperwork or evaporate.

Concept

Architecture: what "DDC per equipment, BMS on top" means on drawings

Each air-handling unit, fresh-air unit, fan set and packaged unit has its own direct digital controller running its sequence stand-alone; a failure of the BMS network leaves every unit running on its last set points. The BMS server supervises: schedules, trends, alarms, set-point changes, energy reports. VRF systems are proprietary networks; they reach the BMS through a gateway (BACnet is the design basis's choice) that exposes a limited set of points per indoor unit (on/off, mode, set point, room temperature, fault). The review artefacts are the system architecture diagram, the points list (inputs and outputs per controller, hard-wired versus network), the sequence of operation for each system, the alarm list with priorities, and the panel schedule with IP ratings and locations.

Sequences to read line by line

  • Room units on VRF: wired thermostat per room; set-point range limited (for example 22–26 °C) so occupants cannot drive the system to 16 °C; dead band between cooling and any heating; occupancy or key-card interlock in accommodation if the client wants it.
  • Treated fresh-air unit: supply temperature control at 20–23 °C after the heat pipe; the cooling coil controlled on off-coil temperature (dew point), not on supply temperature, so that moisture removal is guaranteed; wheel or plate bypass logic; filter differential alarms; fan on variable speed with a minimum outdoor-air floor per ASHRAE 62.1 when CO2 control is active.
  • Pressurised rooms: a differential-pressure sensor across the envelope modulating the supply fan or a relief damper; alarm on loss of pressure; airlock door interlocks where +50 Pa is confirmed.
  • Substations and battery rooms: duty/standby changeover on failure and on run-hours, high-temperature alarm and staged response (second unit, then purge), the battery charger interlock and fan status to the fire-and-gas system.
  • Kitchens and laundry: hood exhaust and make-up air interlocked (make-up cannot run without exhaust; exhaust runs on suppression discharge), ecology-unit stage alarms, dryer exhaust interlocked to dryer operation.
  • Demand-controlled ventilation: CO2 set point (typically 800–1,000 ppm, or 700 ppm above outdoor), sensor in the space rather than the return duct for large halls with stratification, and a hard floor at the 62.1 area-based rate.
  • Fire interfaces: hard-wired shutdown from the fire alarm panel independent of the BMS network; damper end-switches; status back to BMS (Module 9).

Kahramaa: the permit-side energy check

The Energy & Water Conservation Code (2016, re-issued 2023 as CN-CNT-P2/C1 and 2025 as CN-CNT-P2-C2 Issue 2) is applied at the building permit through Kahramaa's engineer. What it asks for, from the recovered text: envelope U-values and glazing SHGC certified by the manufacturer and calculated for summer per ASHRAE; a cooling-load summary sheet and a cooling-equipment schedule for verification; loads by acceptable handbooks or ASHRAE-certified software; equipment efficiencies against its tables (Module 5), with chillers pointed to ASHRAE 90.1 Table 6.8.1-3 in the 2025 issue and unlisted equipment to ASHRAE 90.1 §6.4.1; polyphase motors IE2 or better (2023 issue); the air-conditioner star label for unitary units; and, through the Wiring Code, the declared AC load with connected and diversified demand per distribution board at power factor 0.9 or better. The summary sheet is the HAP block-load report reformatted; the schedule is the equipment schedule you reviewed in Module 5. Inconsistency between them is the most common reason for a Kahramaa return.

GSAS: the certification-side energy and indoor-environment check

GSAS Design & Build (2019, 4th edition) scores a building from −1 to +3 across categories; certification requires a positive score and stars follow half-point bands (1 star from 0 to 0.5, up to 6 stars above 2.5). The HVAC-relevant criteria: E.1 thermal energy demand performance (envelope and internal gains, the same inputs as Module 2), E.2 energy use performance (modelled energy against a baseline; equipment efficiency and controls from Modules 5 and 10), E.3 primary energy, E.4 CO2 emissions, E.5 energy sub-metering (the design basis's metering strategy report), IE.1 thermal comfort (ASHRAE 55 predicted mean vote within ±0.5, or operative-temperature compliance), IE.2 natural ventilation, IE.3 mechanical ventilation (ASHRAE 62.1 and the +20 % cap interplay from Module 3), IE.8 acoustics. GSAS is mandatory for government projects and common on the client work; the design basis lists it without a target, which is the first question to put to the client, because a 3-star target changes the envelope, the fresh-air strategy and the equipment class.

ASHRAE 55 in one paragraph

Comfort is operative temperature, humidity, air speed, clothing and activity together; the standard's compliance zone at 0.5 clo and sedentary activity spans roughly 23–26 °C operative at 50 % RH, and it caps the humidity ratio at 12 g/kg for the analytical method. The design basis's 22 ± 1 °C with 40–60 % RH sits at the cool edge of the zone, which is a client preference; the reviewer's check is that the room units can actually hold it at part load without over-cooling (Module 2's cycling problem) and that air speed at the occupant stays below 0.2 m/s for NR 30 bedrooms.

Read

  • A
    HVAC Design Guidelines (corporate extract) §10.2 — BAS control tolerances (space ±1.1 K, RH ±5 %, airflow ±5 %), ASHRAE 135 BACnet, and the 929 m² threshold for requiring a BAS; a compact template for an owner's controls expectations.
  • B
    Dubai Green Building Regulations 502.02 (demand-controlled ventilation), 502.08 (control systems for HVAC), 502.10 (exhaust-air energy recovery) and 503 (commissioning and management) — the regional statement of the same controls and energy rules Kahramaa and GSAS apply.
  • C
    ASHRAE Design Manual Chapter 3 (occupant comfort and health; Standard 55 air-speed limits 0.15 m/s winter / 0.25 m/s summer) and Chapter 10 (controls, in the full edition).
  • D
    design basis Annex A Table 3-11 (Kahramaa 2016 efficiency tables) — the compliance yardstick until the 2025 code is obtained.

Qatar rules that touch this module

  • Partial
    Kahramaa Energy & Water Conservation Code 2016 / 2023 (CN-CNT-P2/C1, 29 May 2023) / 2025 (CN-CNT-P2-C2 Issue 2, 18 Sep 2025, 27 pp) — envelope, load summary and equipment schedule submittal, efficiency tables, IE2 motors, insulation for all air-conditioned new buildings. Clause numbers to be confirmed from the PDFs on km.qa.
  • Verified
    Kahramaa Electricity Wiring Code 2018 (CS-CSI-P1/C1) and EPP-C1 Electricity Planning Issue 5 (2020) — AC load declaration with the permit, connected and diversified load, power factor ≥ 0.9, supply 415/240 V 50 Hz.
  • Verified
    GSAS 2019 D&B: E.1–E.5, IE.1–IE.8; score −1 to +3; stars in 0.5 bands; mandatory for government projects; adopted as GSO 3000:2025 — no national minimum star level for industrial or oil-and-gas buildings found; the client fixes it in the contract.
  • Verified
    ASHRAE 90.1-2019/2022 §6.4 and §6.5 (controls, fan power, energy recovery, DCV) and ASHRAE 55-2020 — the technical basis both regimes lean on; ASHRAE 135 BACnet for the integration the design basis specifies.
  • Verified
    QCS 2014 Section 7 Green Construction — declares GSAS the foundation for green construction with its Energy, Water, Indoor Environment and Management categories mandatory.

Review checklist: controls submittals and energy compliance packages

Self-check

  1. Why must a treated-fresh-air unit's cooling coil be controlled on off-coil (dew-point) temperature rather than on supply temperature?

  2. The Kahramaa cooling-load summary shows 1,850 kW for a building whose equipment schedule totals 2,400 kW. Is that a problem?

  3. What does a BACnet gateway to a VRF system typically not give the BMS?

  4. GSAS is listed in the design basis. What is the single question to ask, and why does it matter to HVAC?

  5. Where should CO2 sensors be placed for demand control in the Friday mosque, and what floor must the control respect?

  6. Name the two Kahramaa submittals that come directly from documents you reviewed in Modules 2 and 5.

Flashcards

Next: Module 11, testing, balancing and commissioning.

Week 3 · Module 11 · about 1.5 hours

Testing, balancing, commissioning and handover

Design intent becomes measured fact in three stages: construction verification (leak and pressure tests), balancing (air quantities within tolerance), and functional testing (sequences, interlocks, fire responses). Your construction-phase role, site queries, non-conformances, punch lists and completion reports, is built on the same documents. This module sets the acceptance criteria before the first report arrives.

Why it matters

A balancing report with airflows "within tolerance" against an unstated tolerance proves nothing. A fire-alarm shutdown test done with the BMS network up proves the wrong path. A VRF circuit commissioned in December will be fine in December. The reviewer who fixed the acceptance criteria at the procedure stage spends the summer reading numbers; the one who did not spends it in meetings.

Concept

The sequence and its documents

StageWhat is provedDocumentAcceptance basis to fix in advance
Factory acceptancePackaged units, ecology units, large fans perform and are built as specifiedFAT procedure and report; witness points in the ITPCapacity at a stated test condition with correction to 47 °C; sound power; coating certificates; nameplate data
Construction verificationDucts, pipes and insulation are installed to the standardInspection and test plan; duct leakage test (DW/143 or SMACNA); refrigerant pressure and vacuum records; condensate flood test; insulation and vapour-barrier inspection before closing ceilingsLeakage class and test pressure per pressure class; 4.15 MPa / 24 h and ≤ 500 microns for R-410A; 1 % condensate slope; damper access verified
Pre-commissioningEquipment is safe to startPre-commissioning checklists (rotation, alignment, safeties, filters, dampers open, strainers)Manufacturer's start-up checklist signed; mechanical completion certificate per system
Testing, adjusting and balancingAir (and water) quantities match design within toleranceTAB report to NEBB, AABC or CIBSE Commissioning Code A proceduresTypically ±10 % on terminals, −0/+10 % on totals, ±5 % where the specification says critical; fan curves marked with the operating point; pressurisation ΔP and door forces recorded
Functional performance testingSequences and interlocks workFPT scripts per system; cause-and-effect test with the fire alarm contractor and QCDD witness; BMS point-to-pointEvery row of the cause-and-effect matrix executed; shutdown proven with BMS network disconnected; changeover, run-on and interlocks timed
Performance verificationRooms hold design conditions at design loadSeasonal test (summer) with logged temperature and RH; noise (NR in rooms, dB(A) at 1 m outdoors); IAQ where GSAS requires22/23/24 ± 1 °C, 40–60 % RH over a hot-humid period; NR 30/35/40 by octave-band measurement; 65 dB(A) at 1 m
HandoverThe owner can operate itO&M manuals, as-built drawings, training records, spares, warranty register, completion certificates (QCDD, Kahramaa, client)Client's commissioning and handover procedure; punch list closed to category

Tolerances: the number that must be written before the test

NEBB and AABC procedures accept terminal airflows within ±10 % of design and totals within −0 % / +10 %; CIBSE Commissioning Code A uses similar bands with tighter values for critical rooms. Outdoor-air quantities are a minimum, never a −10 %. Pressurisation is accepted on measured differential pressure with the doors closed and on door force with the system running. QCS Section 22 Part 1 has its own testing clauses whose tolerances must be read and reconciled with the specification; where the specification is silent, state the NEBB values in your review of the TAB procedure so the report cannot be "within tolerance" of nothing.

The summer problem

Cooling systems commissioned in a Qatar winter cannot demonstrate capacity or dehumidification. Either the contract holds a seasonal performance test (a logged week in July–September with rooms at set point and RH inside 40–60 %) as a condition of final acceptance, or the reviewer accepts that the first real test is the first summer under warranty. Write the seasonal test into the commissioning plan now; it costs nothing at the procedure stage and everything at the punch-list stage.

Construction-phase instruments you will run

  • Site queries and RFIs: the design answer must cite the design basis or specification clause it relies on; an RFI that changes a design criterion is a change, not a clarification, and goes through the change-management system.
  • Non-conformance reports: categorise by consequence (safety and code compliance; performance; durability; cosmetic); a duct leakage test failure is a performance NCR with a retest, an uninsulated suction line behind a closed ceiling is a durability NCR with an open-up.
  • Punch lists: category A (prevents safe operation or occupancy: fire damper missing, cause-and-effect row failed), B (prevents design performance: airflow out of tolerance, missing balancing damper), C (cosmetic or documentation). Mechanical completion is A-clear; substantial completion is A and B clear with C scheduled.
  • Mechanical completion report: per system, lists the tests performed with results against the acceptance criteria, the open punch items by category, the deviations accepted, and the documents handed over. It is the document the client's handover procedure will audit.

Read

  • A
    HVAC Design Guidelines (corporate extract) — ASHRAE 111 (measurement, testing, adjusting and balancing) in the code list; BAS tolerances (airflow ±5 %, water flow ±5 %, pressure differential ±5 %) as an example of an owner tightening the balancing bands.
  • B
    Dubai Green Building Regulations 502.13 (ductwork air-leakage testing before occupancy for systems above 250 Pa and all outdoor/unconditioned ductwork) and 503.01 (commissioning) — a regulation that makes the tests mandatory rather than optional.
  • C
    ASHRAE Design Manual Chapter 2 — the design process through commissioning; the design-review and documentation stages an owner's process expects.

Qatar rules that touch this module

  • Partial
    QCS 2014 Section 22 Part 1 (testing, commissioning, maintenance and warranty; O&M instructions; inspection) and Section 1 Part 10 / Section 11 (health and safety, heat stress) — testing clauses and tolerances to be confirmed from the PDF; the H&S sections govern summer site work.
  • Verified
    QCDD completion certificate and maintenance requirements ("Maintenance – Mechanical") — periodic testing of smoke control, pressurisation and HVAC shutdown on alarm; the functional tests at handover become the baseline.
  • Verified
    Kahramaa connection and completion — final AC load and metering per the Wiring Code; smart meters; the permit's cooling-load summary is checked against the installed schedule.
  • Unverified
    the client the client's commissioning and handover procedure Procedure for Project Commissioning and Handover — not public; obtain it: it defines mechanical completion, pre-commissioning, commissioning and handover certificates and the punch-list categories the client will apply.
  • Verified
    NEBB / AABC procedural standards; CIBSE Commissioning Code A; DW/143; ASHRAE 111; ASHRAE Guideline 0 and Standard 202 (commissioning process) — the procedure families to cite in the commissioning plan.

Worked example: reading a balancing report for an accommodation floor

1
Design: 12 hi-wall units (no ducts, so no TAB), one corridor ducted unit 420 L/s, four toilet extract fans each 80 L/s (10 ACH), stair pressurisation not required. Report shows corridor supply 372 L/s (−11 %), extracts 70–95 L/s.
2
Corridor: −11 % is outside ±10 %; the fan is at 480 Pa against a 400 Pa design (dirty filter installed during construction, undersized flexible connections) → NCR category B, rebalance after filter change and re-test.
3
Extracts: 70 L/s (−12.5 %) on two fans fails; 95 L/s (+19 %) on one passes the terminal tolerance but pulls the far unit down; require damper adjustment and re-test all four together. Toilet-extract shortfall matters twice here: it is the only ventilation driver for the bedrooms.
4
Pressure check: with extracts running, corridor-to-outside −4 Pa, bedroom-to-corridor −2 Pa: the block is negative to outside, as the untreated-ventilation concept intends, but the corridor is now negative to the stair; check the fire strategy's stair separation requirement before accepting.
5
Missing from the report: tolerance basis, instrument calibration certificates, fan curve with operating point, ambient conditions during test. Return the report with those four items listed.
A balancing report is accepted on four things: the tolerance it was measured against, the instruments, the system state during the test, and every terminal inside the band. Three of the four are usually missing the first time.

Review checklist: commissioning plan, procedures and reports

Self-check

  1. A TAB report states all terminals "within tolerance". What is your first question?

  2. Why test the fire-alarm HVAC shutdown with the BMS network disconnected?

  3. Which category is an uninsulated suction line found behind a closed ceiling, and why?

  4. Outdoor air measured at 1,950 L/s against 2,136 L/s design (−8.7 %). Pass or fail?

  5. What does a mechanical completion report contain that a TAB report does not?

  6. Why write the seasonal test into the plan at the procedure stage?

Flashcards

Next: Module 12, review drills, the inconsistency register and the regulation ledger.

Week 3 · Module 12 · 1.5 hours and then ongoing

Capstone: review drills and the registers you carry into every review

Three seeded documents to review cold, with answer keys. Then the two working registers: the design-basis inconsistency register with draft comment wording, and the Qatar regulation verification ledger. Print the registers; they are the part of this guide you will use after the modules are forgotten.

Drill 1: cooling-load summary (find at least six issues)

ItemValue stated
SpaceJunior Clubhouse, lounge, 180 m², 3.6 m high, ground floor, south and west glazing 22 m² (SC 0.55)
Software / methodCarrier HAP 4.9, ASHRAE TFM; weather: Doha (HAP default), design 46 °C DB / 29 °C WB
Indoor22 °C / 50 %
EnvelopeWall U 0.568; roof n/a; glazing U 3.3
Occupancy36 persons, seated at rest 70 / 45 W, schedule "office 08–18"
Lighting / equipment10 W/m²; 20 W/m²
VentilationASHRAE 62-2001, 8 L/s per person = 288 L/s; treated centrally; load at 47/30
Infiltration0 ACH
SafetyHAP zone factors 10 % S / 10 % L; schedule multiplied by 1.2
ResultSensible 24.1 kW, latent 4.2 kW, total 28.3 kW → FCU schedule 34 kW (3 × 11.3 kW)
  1. Write your comments, then compare.

Drill 2: VRF equipment schedule (find at least seven issues)

FieldValue stated
Outdoor unit ODU-J2-01Heat-pump VRF, R-410A, 56.0 kW cooling (nominal), EER 3.8, 415 V / 3 ph / 50 Hz, FLA 32 A
Connected indoor units26 hi-wall 2.8 kW + 1 ducted 5.6 kW = 78.4 kW; connection ratio 140 %
Block load served51 kW (HAP)
PipingLongest actual 172 m; after first branch 38 m; ODU above IDU 12 m; total 640 m
RefrigerantFactory 11.5 kg + additional 27 kg = 38.5 kg
Smallest roomBedroom 12 m² × 3.0 m
Casing / coilPowder coated; hydrophilic blue fin
Sound58 dB(A) (no distance, no bands)
EnclosuresIP54
Operating range−5 to 46 °C
ControlsProprietary central controller; BMS integration "available"
  1. Write your comments, then compare.

Drill 3: duct layout excerpt, accommodation corridor and bedrooms (find at least six issues)

SectionAirflow L/sSize mmNote on drawing
Corridor main from ducted unit420300 × 250"DW-142, low pressure"
Branch to bedroom diffuser (transfer)60200 × 150VCD at diffuser neck
Roof run to TFAHU900500 × 30025 mm insulation, no cladding
Crossing corridor wall to stair lobby (2 h)420300 × 250no damper shown
Downstream of cooling coil, TFAHU900"25 mm acoustic lining, 3 m"
Fresh-air intake louvre900600 × 600 sand-trap"3 m from toilet exhaust discharge"
Leakage / pressure classnot stated
  1. Write your comments, then compare.

Build your own inconsistency register

Read the design basis once with a blank table beside you: reference, issue, severity (H changes a selection or safety function; M changes a quantity or document; L editorial) and a draft comment written to be pasted into a comments resolution sheet. Typical findings on Gulf projects: two outdoor design points without stated use; RH criteria with no humidity control; compounded safety factors; process-plant pressurisation tables copied into non-process buildings; system-per-building lists that disagree with each other; no redundancy philosophy; withdrawn standards (BS 5588, ASHRAE 52.1, DW/142); missing duct, insulation and piping criteria; deferred kitchen and laundry loads; and a green-building rating listed without a target.

Qatar regulation verification ledger

Status reflects what could be verified from this workstation on 3 September 2026: government portals (qcs.qs.gov.qa, km.qa, moi.gov.qa, gord.qa, qatarenergy.qa) and ashrae-meteo.info were not reachable, so clause-level facts rest on indexed text and authoritative summaries. Close each open item by opening the document and recording the clause.

InstrumentIssuer / editionHVAC relevanceStatusTo close
Law 4/1985 (buildings), Law 13/1997 as amended by 9/2012 (civil defence), Decision 210/2014 (QCS 2014 mandatory), Decision 15/2024 (QCS 2024 optional), Law 19/2024 (district cooling)State of QatarLegal basis for permits, QCDD review, QCS status, DC regulationVerified
QCS 2014 Section 22 Parts 1–9; Sections 9/22, 14/4, 15, 19, 20, 21, 23, 7Ministry of Municipality / Qatar Standards, 2014Design data, equipment, ductwork, insulation, fans, accessories, 65 dB(A) at 1 m, 0–55 °CPartialOpen Section 22 PDF; record clause numbers for design data, Part 6 duct standard/leakage, Part 7 thickness tables, Part 1 T&C tolerances, Part 4 clause 4.6
QCS 2024 (QS 27/2024)Qatar Standards, 2024Declared superseding but optional; Section 22 structure unconfirmedPartialConfirm contract edition; compare Section 22 part list
Kahramaa Energy & Water Conservation Code 2016 / 2023 (CN-CNT-P2/C1) / 2025 (CN-CNT-P2-C2 Issue 2)Kahramaa TarsheedWall 0.568, roof 0.44, glazing U 3.30 / SHGC 0.30 (≤ 40 % WWR); load summary and equipment schedule submittal; efficiency tables (Annex A Table 3-11); IE2 motorsPartialOpen the 2025 PDF; record U-value/SHGC table, efficiency clauses, ASHRAE 90.1 edition cited
Kahramaa Electricity Wiring Code 2018 (CS-CSI-P1/C1); EPP-C1 Issue 5; Water Installation Code 2016Kahramaa415/240 V 50 Hz; AC load declaration; PF ≥ 0.9; water interfacesVerifiedCheck for any post-2018 re-issue
QS 2663 (SASO 2663) AC star ratingQGOSM / Kahramaa, enforced July 2016Minimum 3 stars, T3 test, scope ≤ ~70,000 Btu/h unitaryVerified
District Cooling Code 2016; 2013 directive banning potable water for cooling towersKahramaa / MMETSE-only cooling towers; DC regulationVerified
QCDD Technical Requirements Guide 2022 (2023 update); 2015 annexes FLS_A1–A8, FFS, FAS, ACMV_N1; car-park annex FSS 7.2; DC1/DC2 processMoI General Directorate of Civil DefenceSmoke control, pressurisation, dampers, special-room ventilation, NFPA adoption, approvalsPartialOpen guide_english.pdf; record chapter numbers, ACMV_N1 numeric criteria, NFPA edition enforced
GSAS 2019 D&B (4th ed.): E.1–E.5, IE.1–IE.8; GSO 3000:2025GORDEnergy and indoor-environment criteria; star thresholdsPartialProject target rating from client; refrigerant criterion code from the D&B manual
Client corporate standards: building-services minimum design requirements, workers-accommodation regulation, fire and safety philosophy, commissioning and handover procedure, fire life safety strategy, metering strategy, cooling-system comparison report; industrial-city permit guidelinesClient / operatorLevel-1 requirements: pressurisation, fire-and-gas dampers, commissioning, permits inside industrial citiesUnverifiedObtain from client document control; cite clause numbers in your comments
ASHRAE climatic data, Doha 411700 (Fundamentals 2017/2021/2025; Standard 169-2021)ASHRAE0.4 % DB/MCWB, WB/MCDB, DP/HR; climate zone (0B expected)PartialOpen ashrae-meteo.info; record values and dataset year used by HAP
Montreal Protocol status; HPMP Stage II/III; Kigali not ratified (Oct 2025)MoECC National Ozone Unit / UNEPHCFC phase-out 2030; no HFC phase-down; A2L rules absentVerifiedCheck ozone.unep.org for 2026 ratification
MME Building Permit guides (2022); e-BP routing (Kahramaa, QCDD, Ashghal)Ministry of MunicipalityWhich authority checks which HVAC documentPartialOpen the Building Requirements Guide 3rd ed. for the HVAC drawing checklist
API RP 500/505; IEC 60079-10-1, 60079-13; NFPA 496; ISO 15138; NFPA 90A/92/96/37/20/110/101/5000 current editions; ASHRAE 15/34/55/62.1/90.1/170; DW/144; SMACNA; IEC 62485-2; BS EN 12101-6Standards bodiesInternational references invoked by the design basis or this guideVerifiedConfirm editions in the project specification
Reference map, glossary and unit conversions follow.

Reference

Reference map, glossary, conversions and sources

Where each module's evidence lives, the vocabulary a Gulf HVAC submittal assumes, the conversions you will do in your head, and an honest statement of how this guide was built.

Reference map: module → library file → Qatar instrument

ModuleLibrary files (Drive)Qatar and client instrumentsDesign-basis sections
M0 OrientationLaw 4/1985; QCS 2014 status; MME e-BP routingdesign basis front matter and code list
M1 PsychrometricsPsychrometric chart; 1997 Fundamentals Ch. 28; PDH M196; Castillo Part 1QCS 22 Part 1 design data; ASHRAE 169 / Fundamentals Ch. 14 Doha 411700; Dubai GBR 501.03Design conditions section
M2 Cooling loadM196; 1997 Ch. 28; Castillo Part 2 (HAP); ASHRAE Design Manual; BR 443; U-values; Materials; TM37; Infiltration; Mitsubishi manual and Load_estimate.xlsKahramaa code 2016/2025 (envelope, load summary); QCS 14/15; GSAS E.1/E.2Load-calculation criteria
M3 VentilationASHRAE 62.1-2013; HVAC Design Guidelines; Design Manual; M196QCS 22 Part 4; GSAS IE.2/IE.3; QCDD ACMV_N1; BS EN 12101-6; NFPA 92; IEC 60079-13Ventilation and pressurisation criteria
M4 Systems / VRFDesign Manual; McQuay AG 31-011; HVAC Design Guidelines; Dubai GBRQCS 22 Parts 2–3; 2014 cooling-tower directive; Law 19/2024; Montreal Protocol status; ASHRAE 15/34; ISO 12944System philosophy
M5 EquipmentNC/NR sheet; Design Manual; Dubai GBR; Mitsubishi manualQS 2663; Kahramaa code tables; Wiring Code 2018; QCS 22 Parts 1, 3, 9; ASHRAE 90.1 Table 6.8.1Equipment criteria
M6 DuctsDuct sizing chart; NC/NR sheet; HVAC Design Guidelines; Dubai GBR; Design ManualQCS 22 Parts 6, 7, 9; QCDD; NFPA 90A; DW/144; SMACNA; ASHRAE 62.1 §5.4Duct design criteria
M7 PipingMcQuay AG 31-011; Suva piping handbook; Condensate note; CHW sizing verificationQCS 22 Parts 2, 3, 7; QCS 19/20; IMC 307; ASHRAE 15; BS 5422Piping criteria
M8 Special roomsBattery room (EXIDE); 62.1 Table 6.5; TM37; HVAC Design GuidelinesQCDD annexes A5–A8; NFPA 37/20/110/96; IEC 62485-2; ASHRAE 170; IEC 60079-13; client building-services standardsSpecial-room criteria
M9 Fire interfacesHVAC Design Guidelines; Dubai GBR 401.09Law 13/1997; QCDD 2022 guide and annexes; DC1/DC2; NFPA 90A/92/96/101; the client's fire and safety philosophy; fire life safety strategyFire and smoke sections
M10 Controls / energyHVAC Design Guidelines §10.2; Dubai GBR 502/503; Design Manual Ch. 3Kahramaa code and Wiring Code; GSAS E/IE; ASHRAE 90.1, 55, 135; QCS Section 7Controls and energy sections
M11 CommissioningHVAC Design Guidelines; Dubai GBR 502.13/503; Design Manual Ch. 2QCS 22 Part 1; QCDD maintenance; Kahramaa completion; the client's commissioning and handover procedure; NEBB/AABC/CIBSE Code A; DW/143Commissioning section
Files not usable without further work: Load_estimate.xls (legacy .xls, not readable here), the condensate table (embedded image), the KAIA duct chart (image), the chilled-water verification table (image). The ASHRAE Design Manual text in the library ends at page 79 (Chapters 6–10 missing). TRANE Load Calculation .rar and the fire-flow spreadsheets in the first folder are outside HVAC scope.

Glossary

ACH
Air changes per hour: airflow ÷ room volume × 3,600. Always say which air: supply, outdoor or exhaust.
AHU / FAHU / TFAHU
Air-handling unit; fresh-air handling unit; treated fresh-air handling unit (fresh air cooled, dehumidified and reheated before delivery).
AHRI
Air-Conditioning, Heating and Refrigeration Institute (formerly ARI): equipment rating standards 210/240, 340/360, 390, 550/590, 1230.
design basis
Basis of Design: the document that freezes site conditions, criteria, systems and code hierarchy.
Block load
The largest simultaneous load on a system, smaller than the sum of zone peaks by the diversity between zones.
CLTD / CLF / SCL
Cooling-load temperature difference, cooling-load factor, solar cooling load: the 1990s manual-method tables.
Connection ratio
VRF: sum of indoor-unit nominal capacities ÷ outdoor-unit nominal capacity, in percent.
CRS
Comments resolution sheet: the client's review comments and the designer's responses, revision by revision.
DC1 / DC2
Qatar Civil Defence drawing-approval stages: life safety, then fire alarm, firefighting and mechanical ventilation.
DCV
Demand-controlled ventilation: outdoor air modulated on CO2 or occupancy above a fixed floor.
DDC
Direct digital control: a stand-alone controller running a sequence for one system.
DW/144, DW/143
BESA (UK) sheet-metal ductwork specification and its leakage-testing companion.
ERU / ERV
Energy-recovery unit or ventilator: wheel or plate exchanging heat (and moisture) between exhaust and fresh air.
ESP
External static pressure: the resistance outside the unit that its fan must overcome.
EER / COP / IEER / IPLV / SEER
Full-load and part-load efficiency metrics; EER in Btu/h per W, COP in W/W (EER = 3.412 × COP).
FACP / FAS
Fire alarm control panel / fire alarm system.
FCC
Fire command centre.
GSAS
Global Sustainability Assessment System (GORD, Qatar); Design & Build rating 1–6 stars.
HAP
Carrier Hourly Analysis Program: load calculation and energy simulation software.
IDU / ODU
Indoor / outdoor unit of a split or VRF system.
IP rating
Ingress protection per IEC 60529 (first digit solids, second liquids): IP55 dust-protected and jet-protected; IP64/65/66 dust-tight.
Kahramaa
Qatar General Electricity and Water Corporation: utility, permit checker for energy conservation and AC load.
MAHU
Make-up air handling unit: replaces kitchen hood exhaust with cooled outdoor air.
MERV
Minimum efficiency reporting value, ASHRAE 52.2 filter grade (MERV 8 pre-filter, MERV 13 fine).
NR / NC / RC
Noise rating (ISO/UK), noise criterion (US), room criterion (ASHRAE): single-number room noise targets from octave-band spectra.
QCDD
Qatar Civil Defence Department (General Directorate of Civil Defence, Ministry of Interior).
QCS
Qatar Construction Specifications (2014 mandatory; 2024 optional edition).
RCL
Refrigerant concentration limit (ASHRAE 34), kg per m³ of occupied room.
RTS / TFM
Radiant time series / transfer function method: hourly load-calculation engines.
Sand-trap louvre
Inertial intake louvre that drops sand before the filters; sized at about 1 m/s gross face velocity.
SC / SHGC
Shading coefficient (relative to 3 mm clear glass) / solar heat gain coefficient (fraction); SHGC ≈ 0.87 × SC.
SHR
Sensible-heat ratio: sensible ÷ total load or capacity.
T1 / T3
ISO 5151 rating conditions, 35 °C and 46 °C outdoor.
TAB
Testing, adjusting and balancing.
TR
Ton of refrigeration = 3.517 kW = 12,000 Btu/h.
TSE
Treated sewage effluent: the only water permitted for cooling towers in Qatar.
VCD
Volume control damper.
VRF / VRV
Variable refrigerant flow (VRV is Daikin's trade name): one inverter outdoor unit serving many indoor units.
WMO 411700
Doha International Airport, the ASHRAE climatic station for Qatar.

Unit conversions

QuantityConversionMental shortcut
Cooling1 TR = 3.517 kW = 12,000 Btu/h; 1 kW = 3,412 Btu/hkW × 0.284 = TR; TR × 3.5 = kW
Airflow1 L/s = 2.119 cfm; 1 m³/h = 0.278 L/s; 1 m³/s = 2,119 cfmcfm ÷ 2 ≈ L/s (+6 %)
Pressure1 in. w.g. = 249 Pa; 1 Pa = 0.004 in. w.g.; 1 bar = 100 kPa250 Pa per inch
Friction rate1 in. w.g. per 100 ft = 8.17 Pa/m; 0.1 in./100 ft = 0.82 Pa/mPa/m × 0.12 = in./100 ft
Velocity1 m/s = 196.9 fpm; 500 fpm = 2.54 m/s; 1,000 fpm = 5.08 m/sfpm ÷ 200 = m/s
Area / density1 m² = 10.76 ft²; 1 W/m² = 0.093 W/ft²; 1 W/ft² = 10.76 W/m²W/ft² × 10.8 = W/m²
Load densityft²/ton × 0.0264 = m²/kW; 450 ft²/ton = 11.9 m²/kW = 84 W/m²m²/kW = 1,000 ÷ (W/m²)
EfficiencyEER (Btu/h·W) = 3.412 × COP; kW/TR = 12 ÷ EER = 3.517 ÷ COPEER 10 ≈ COP 2.9 ≈ 1.2 kW/TR
InsulationR-value (h·ft²·°F/Btu) × 0.176 = m²K/W; R-10 = 1.76 m²K/W; U (Btu/h·ft²·°F) × 5.678 = W/m²KU 0.1 imperial ≈ 0.57 SI
Refrigerant pressure1 MPa = 10 bar = 145 psi; R-410A design 4.15 MPa ≈ 41.5 bar ≈ 600 psi
Temperature difference1 K = 1.8 °F; 2 °F = 1.1 K

How this guide was built, and what it does not claim

  • The twenty-three files in the four reference folders were read and catalogued; four are images or legacy formats that could not be parsed (noted in the reference map). Quoted numbers come from the files themselves.
  • Qatar regulations were researched from public sources on 3 September 2026. Government portals were not reachable from the build environment, so clause-level statements from QCS, Kahramaa, QCDD and GSAS carry "Partial" badges and a closing action in the ledger; the client standards are not public and carry "Unverified" badges.
  • Worked examples use stated assumptions and simplified envelope terms; they teach structure and magnitude, not a design.
  • Rules of thumb labelled as such (Gulf W/m² bands, derating percentages, insulation thicknesses) are experience values for screening, not acceptance criteria; the project specification governs.
  • Nothing here replaces the project specification, the client's standards, or the judgement of the engineer of record.